Question

Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101...

Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101 and Job 102 showed the following information:

Job 101 Job 102
Direct Materials $ 12,000 $ 15,000
Direct labor 24,000 45,000



If overhead is applied to jobs at $0.80 per direct labor dollar, the total manufacturing overhead cost for the two jobs would be:

Multiple Choice

$96,000.

$162,000.

$55,200.

$151,200.

Gibbons Company uses a process cost system and the weighted average method. The company had 400 units of product in its work in process inventory at the beginning of the period. During the period 1,500 additional units of product were started. At the end of the period there were 750 units of product in the work in process account. The ending work in process inventory was estimated to be 30% complete. The beginning work in process inventory had a cost of $2,000. Product costs totaling $42,000 were added to work in process during the period. The number of equivalent whole units in ending work in process is:

Multiple Choice

750.

1,275.

450.

225.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing...
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 6,600 102 5,280 103 960 $ 3,600 104 4,080 7,200 105 8,400 106 2,900 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 4,100 102 3,200 103 920 $ 2,000 104 2,100 4,500 105 5,700 106 3,800 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
Atlantic Manufacturing Corp operates a job-order costing system and applies overhead cost to jobs on the...
Atlantic Manufacturing Corp operates a job-order costing system and applies overhead cost to jobs on the basis of direct labor cost. The company has provided the following data: (Amounts in dollars $) Estimated direct labor cost              85,000 Actual direct labor cost              87,000 Estimated manufacturing overhead costs           148,750 Actual manufacturing overhead costs           147,300 Purchases of raw materials (all direct)           141,000 Beginning Ending Raw materials              23,000                   16,000 Work in Process              44,000                   36,000 Finished...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current year. The predetermined overhead rate is 30% of direct labor costs. The following cost information is available (all materials and time ticket information apply to direct costs): Job Material Requisitions Time Tickets 101 $91,000 $36,000 102 $67,000 $62,300 103 $47,000 $55,500 104 $35,700 $42,000 105 $39,000 $92,750 Part 1—Complete the job cost sheets for each job. Job No. 101 Job No. 102 Job No....
1. The overhead cost applied to a job during a period is recorded with a credit...
1. The overhead cost applied to a job during a period is recorded with a credit to Factory Overhead and a debit to: Multiple Choice Jobs Overhead Expense. Cost of Goods Sold. Finished Goods Inventory. Indirect Labor. Work in Process Inventory. 2. Job A3B was ordered by a customer on September 25. During the month of September, Jaycee Corporation requisitioned $2,500 of direct materials and used $4,000 of direct labor. The job was not finished by the end of the...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,170. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,030 $3,160 102 3,700 4,270 103 2,450 2,090 104 8,300 7,840 105 5,270 5,970 106 3,850 3,790 For general factory use 1,030 4,680 Factory overhead costs incurred on account, $5,790....
Southwestern Fashions, Inc. which uses a job-order costing system, had two jobs in process at the...
Southwestern Fashions, Inc. which uses a job-order costing system, had two jobs in process at the start of the year: job no. 101 ($84,100) and job no. 102 ($53,500). The following information is available:    a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $824,000, and 16,000 hours, respectively. b. The company worked on four jobs during the first quarter. Direct...
Minstrel Manufacturing uses a job order costing system. During one month, Minstrel purchased $198,000 of raw...
Minstrel Manufacturing uses a job order costing system. During one month, Minstrel purchased $198,000 of raw materials on credit; issued materials to production of $195,000 of which $30,000 were indirect. Minstrel incurred a factory payroll of $150,000, of which $40,000 was indirect labor. Minstrel uses a predetermined overhead application rate of 150% of direct labor cost. Minstrel’s beginning and ending Work in Process Inventory are $15,500 and $27,000 respectively. Compute the cost of jobs transferred to Finished Goods Inventory. Multiple...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Job 86 Job 87 Direct materials $4,800 $1,600 Direct labor 1,200 3,000 Applied overhead 888 2,220 Balance, March 1 $6,888 $6,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT