The information below was taken from the job cost sheets of Bates Company.
Job Number | Manufacturing Costs as of June 30 | Manufacturing Costs in July |
||||||
101 | $ | 4,100 | ||||||
102 | 3,200 | |||||||
103 | 920 | $ | 2,000 | |||||
104 | 2,100 | 4,500 | ||||||
105 | 5,700 | |||||||
106 | 3,800 | |||||||
During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31.
a. Compute the work in process inventory at June 30.
b. Compute the finished goods inventory at June 30.
c. Compute the cost of goods sold during July.
d. Compute the work in process inventory at July 31.
e. Compute the finished goods inventory at July 31.
a)Work in Process at June 30-
Job No 103-920
Job No 104-2100
Total 3020
b)Finished Goods at June 30-
Job No 101-4100
Job No 102-3200
Job No 104-2100
Total 9400
c)COGS during July-
Job No 101-4100
Job No 102-3200
Job No 104-2100
Total 9400
d)Work in Process at July 31-
Job No 105-5700
Job No 106-3800
Total 9500
e)Finished Goods Inventory as at July 31-
Job No 103- 920
Total 920