Question

The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing...

The information below was taken from the job cost sheets of Igmund Manufacturing.

Job Number Manufacturing
Costs as of
June 30
Manufacturing
Costs in July
101 $ 6,600
102 5,280
103 960 $ 3,600
104 4,080 7,200
105 8,400
106 2,900

During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31.

a. Compute the work in process inventory at June 30.

b. Compute the finished goods inventory at June 30.

c. Compute the cost of goods sold during July.

d. Compute the work in process inventory at July 31.

e. Compute the finished goods inventory at July 31.

Homework Answers

Answer #1

Solution 1:

work in process inventory at June 30 = Job 103 and 104 = 960+ 4080 = $5,040

Solution 2:

finished goods inventory at June 30 = Job 101 and 102 = 6600 + 5280 = $11,880

Solution 3:

cost of goods sold during July = Total Cost of  jobs no. 101, 102, and 104

= 6600 + 5280 + 4080 + 7200

= $23,160

Solution 4:

work in process inventory at July 31 = Job 105 and 106 = 8400 + 2900 = $11,300

Solution 5:

finished goods inventory at July 31 = Total cost of Job 103 = 960+ 3600 = $4,560

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 4,100 102 3,200 103 920 $ 2,000 104 2,100 4,500 105 5,700 106 3,800 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing...
Tierney Company begins operations on April 1. Information from job cost sheets shows the following. Manufacturing Costs Assigned Job Number April May June Month Completed 10 $5,700 $5,800 May 11 4,700 4,100 $4,000 June 12 2,100 April 13 6,300 4,600 June 14 6,600 3,800 Not complete Job 12 was completed in April. Job 10 was completed in May. Jobs 11 and 13 were completed in June. Each job was sold for 25% above its cost in the month following completion....
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,170. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,030 $3,160 102 3,700 4,270 103 2,450 2,090 104 8,300 7,840 105 5,270 5,970 106 3,850 3,790 For general factory use 1,030 4,680 Factory overhead costs incurred on account, $5,790....
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 44,000 $ 54,000 $ 53,000 Direct labor 16,000 30,000 41,000 Overhead applied 5,280 9,900 13,530 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $11,000; direct labor, $3,400; and overhead, $1,122. Jobs 103 and 104 were...
Hildreth Company uses a job order cost system. The following data summarize the operations related to...
Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,120. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $1,820 $2,040 102 2,220 2,750 103 1,470 1,350 104 4,990 5,060 105 3,170 3,860 106 2,310 2,450 For general factory use 620 3,020 Factory overhead costs incurred on account, $3,480. Depreciation of machinery and equipment, $1,450. The factory overhead...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the...
As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 31,000 $ 71,000 $ 47,000 Direct labor 10,000 28,300 43,000 Overhead applied 4,600 13,018 19,780 Job 102 was started in production in May, and the following costs were assigned to it in May: direct materials, $14,000; direct labor, $3,900; and overhead, $1,794. Jobs 103 and 104 were...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current year. The predetermined overhead rate is 30% of direct labor costs. The following cost information is available (all materials and time ticket information apply to direct costs): Job Material Requisitions Time Tickets 101 $91,000 $36,000 102 $67,000 $62,300 103 $47,000 $55,500 104 $35,700 $42,000 105 $39,000 $92,750 Part 1—Complete the job cost sheets for each job. Job No. 101 Job No. 102 Job No....
Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101...
Cooper Manufacturing is currently working on two jobs. The job order cost sheets for Job 101 and Job 102 showed the following information: Job 101 Job 102 Direct Materials $ 12,000 $ 15,000 Direct labor 24,000 45,000 If overhead is applied to jobs at $0.80 per direct labor dollar, the total manufacturing overhead cost for the two jobs would be: Multiple Choice $96,000. $162,000. $55,200. $151,200. Gibbons Company uses a process cost system and the weighted average method. The company...
Exercise 2-3 Analysis of cost flows LO C2 As of the end of June, the job...
Exercise 2-3 Analysis of cost flows LO C2 As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs. Job 102 Job 103 Job 104 Direct materials $ 25,000 $ 48,000 $ 64,000 Direct labor 13,000 26,900 39,000 Overhead applied 4,810 9,953 14,430 Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $12,000; direct labor, $3,800;...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time,...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $8,500, direct labor of $3,800, and applied overhead of $3,230. Custom Cabinetry applies overhead at the rate of 85% of direct labor cost. During July, Job 120 is sold (on account) for $25,500, Job 121 is started and completed, and Job 122 is started and still in process at the end of the month. Custom Cabinetry...