Question

Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was started during April, but not completed. The job cost sheets revealed the following costs for April:

Job A Job B Job C
Cost of Jobs in Process, 4.1.2018 $12,700 $1,100
Direct Materials Used $2,700 $9,400 $11,100
Direct Labor $11,400 $9,400 $3,700
Applied Manufacturing Overhead ? ? ?

Required:
If no other jobs were started, completed, or sold, determine the balance in each of the following accounts at the end of April:

a. Work in Process :

b. Finished Goods :

c. Cost of Goods Sold:

Homework Answers

Answer #1

Answer with working notes is given below

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $110,500 of manufacturing overhead for an estimated allocation base of $85,000 direct material dollars to be used in production. The company has provided the following data for the just completed year:         Purchase of raw materials $...
Christopher’s Custom Cabinet Company uses a job order cost system with overhead applied as a percentage...
Christopher’s Custom Cabinet Company uses a job order cost system with overhead applied as a percentage of direct labor costs. Inventory balances at the beginning of 2018 follow: Raw Materials Inventory $ 16,100 Work in Process Inventory 6,600 Finished Goods Inventory 21,700 The following transactions occurred during January: (a) Purchased materials on account for $27,200. (b) Issued materials to production totaling $20,900, 90 percent of which was traced to specific jobs and the remainder of which was treated as indirect...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,170. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,030 $3,160 102 3,700 4,270 103 2,450 2,090 104 8,300 7,840 105 5,270 5,970 106 3,850 3,790 For general factory use 1,030 4,680 Factory overhead costs incurred on account, $5,790....
Lott Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,000, direct labor $12,000, and manufacturing overhead $16,000. As of January 1, Job 49 had been completed at a cost of $90,000 and was part of finished goods inventory. There was a $15,000...
A company which uses a job-costing system, had two jobs in process at the start of...
A company which uses a job-costing system, had two jobs in process at the start of February 2018: Job no. J6 with a cost of $110,000 and job no. F1 with a cost of $22,000. The following information is available: The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,366,000 and 102,000 hours, respectively. The company worked on four jobs during February. Direct materials used, direct...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.80 per machine-hour was based on a cost formula that estimates $232,400 of total manufacturing overhead for an estimated activity level of 83,000 machine-hours. Required: 1. Assume that during the year the company works only 78,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Snappy Company uses job-order costing and applies overhead costs to jobs using a pre-determined overhead rate...
Snappy Company uses job-order costing and applies overhead costs to jobs using a pre-determined overhead rate of $12 per direct labor hour. During 2020, Snappy Company worked on the following jobs Job #16 Job #28 Job #35 beginning cost ............. $3,500 $1,600 $2,000 direct materials used ...... $2,800 $3,700 $2,600 direct labor cost .......... $2,000 $5,300 $3,600 direct labor hours ......... 200 hours 300 hours 280 hours By the end of 2020, Job #16 and Job #28 had been completed....
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V,...
Sigma Corporation applies overhead cost to jobs on the basis of direct labor cost. Job V, which was started and completed during the current period, shows charges of $5,000 for direct materials, $9,700 for direct labor, and $6,596 for overhead on its job cost sheet. Job W, which is still in process at year-end, shows charges of $4,400 for direct materials and $4,400 for direct labor. Required: 1a. Should any overhead cost be applied to Job W at year-end? Yes...