Question

SBB Construction built a building for BBB during 2019 and 2020. Relevant data are summarized below:...

SBB Construction built a building for BBB during 2019 and 2020. Relevant data are summarized below:

Contract amount $ 2,550,000
Cost: 2019 1,100,000
2020 500,000
Gross profit: 2019 650,000
2020 300,000
Contract billings: 2019 1,275,000
2020 1,275,000


SBB recognizes revenue upon completion of the contract. Assume that the company bills in the exact amount of the contract (i.e. the sum of contract billings = the total contract price).

What is the journal entry in 2020 to record revenue?

  • Accounts receivable 1,275,000
    Revenue from long-term contracts 1,275,000
  • Construction in progress 950,000
    Cost of construction 1,600,000
    Revenue from long-term contracts 2,550,000
  • Cost of construction 1,750,000
    Gross profit 800,000
    Revenue from long-term contracts 2,550,000
  • Construction in progress 300,000
    Cost of construction 500,000
    Revenue from long-term contracts 800,000

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood...
Redwood Construction Company uses the percentage-of-completion method of accounting for long-term construction contracts. During 2021, Redwood began work on a $4,300,000 fixed-fee construction contract, which was completed in 2024. Cost Incurred Estimated Additional Cost to Complete 2021 $800,000 $3,200,000 2022 $1,000,000 $2,200,000 2023 $936,000 $1,064,000 For the year 2023, Redwood should have recognized gross profit on this contract of: A)500,000 B)300,000 C)225,00 D)135,000
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Correct answer iconYour answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1100000 each quarter. The total contract price is $13200000 and Oriole estimates total costs of $17300000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2019, Oriole Construction estimates that it is 75% complete with the building; however,...
Part A Two days before the financial year end of 31 December 2019, a major customer...
Part A Two days before the financial year end of 31 December 2019, a major customer requested WT Limited to defer delivering 100,000 units of Product A until 2 January 2020 because the customer’s warehouse had already been closed for the New Year holidays. The customer requested WT Limited to issue the invoice for the goods at the current year end though the goods were delivered on 2 January 2020 and agreed to settle the amount within 30 days after...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into...
Ayayai Construction Company began operations on January 1, 2020. During the year, Ayayai Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Ayayai estimated that it would take 5 years to complete the facility at a total cost of $4,498,000. The total contract price for construction of the facility is $6,045,000. During the year, Ayayai incurred $1,184,040 in construction costs related to the construction project. The estimated cost to complete the contract is...
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....
On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:      2020             2021 Actual costs incurred $ 120,000      $ 204,000 Estimated costs to complete 200,000               -0- Progress billings 112,000        248,000 Collections 110,000        250,000 Instructions (show all supporting calculations) Calculate how much...
During 2017 Nilsen company started a construction job with a contract price of $2,400,000. The job...
During 2017 Nilsen company started a construction job with a contract price of $2,400,000. The job was completed in 2019. the following information was available 2017 2018 2019 cost incurred to date $750,000 $1,540,000 $2,000,000. Estimated cost $1,250,000 $660,000 -0-. Customer billing to date $650,000 $1,750,000 $2,400,000. Cash collection to date $450,000, $1,250,000 $2,250,000. Calculate the estimated gross profit and revenue to be recognized on this contract for the years ended december 31, 2017,2018 and 2019 assuming nilsen recognizes revenue...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT