Question

Beavis Construction Company was the low bidder on a construction project to build an earthen dam...

Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below:

2012 2013
  Costs incurred during the year $ 450,000 $1,100,000   
  Estimated costs to complete 1,050,000 0   
  Billings during the year 400,000 1,400,000   
  Cash collections during the year 300,000 1,500,000   

Assume that Beavis recognizes revenue on this contract over time according to percentage of completion.

Required:
Compute the amount of gross profit recognized during 2012 and 2013.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Part A Two days before the financial year end of 31 December 2019, a major customer...
Part A Two days before the financial year end of 31 December 2019, a major customer requested WT Limited to defer delivering 100,000 units of Product A until 2 January 2020 because the customer’s warehouse had already been closed for the New Year holidays. The customer requested WT Limited to issue the invoice for the goods at the current year end though the goods were delivered on 2 January 2020 and agreed to settle the amount within 30 days after...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                         2017                2018 Costs incurred during the year                         $1,500 $1,300 Estimated costs to complete                              1,200 0 Billings during the year                                    1,200 1,300 Cash collections during the year                        1,000 1,500 Compute the amount of revenue and gross profit recognized during 2017 and 2018. Assume that McCombs recognizes revenue on this contract over...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705,000. 2022 billings were $2,820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014 and completed in 2015. Cost and other data are presented below: 2014 2015 Costs incurred during the year 1,500,000 2,700,000 Estimated costs to complete 2,500,000 - Billings during the year 1,900,000 2,500,000 Cash collections during that year 1,700,000 2,600,000 Assume that Hardhat Contractors uses the percentage-of-completion method for revenue recognition. Compute the amount of gross profit recognized during 2014 and 2015. 2014 2015 Contract...
Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion....
Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion. At the start of Year 1, Kip enters a contract to build an office building for $100 million. The project is completed by the end of Year 2. The following additional information is available for this project (amounts in millions): YEAR 1 YEAR 2 Costs incurred during each year $20 $70 Costs expected in future $60 0 sallys Year 2 revenue will be:
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT