Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1100000 each quarter. The total contract price is $13200000 and Oriole estimates total costs of $17300000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2019, Oriole Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $17550000 due to unanticipated price increases. Oriole Construction completes the remaining 25% of the building construction on December 31, 2020, as scheduled. At that time the total costs of construction are $18300000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Oriole will recognize for the year ended December 31, 2020? Revenue Expenses
Revenue Expenses
A)$3300000 $ 4575000
B)$3300000 $ 5137500
C)$13200000 $18300000
D)$4575000 $ 4575000
Feel free to ask any clarification if required. Please provide feedback by thumbs up if satisfied. It will be highly appreciated. Thank you.
Get Answers For Free
Most questions answered within 1 hours.