Question

Part A Two days before the financial year end of 31 December 2019, a major customer...

Part A

Two days before the financial year end of 31 December 2019, a major customer requested WT Limited to defer delivering 100,000 units of Product A until 2 January 2020 because the customer’s warehouse had already been closed for the New Year holidays. The customer requested WT Limited to issue the invoice for the goods at the current year end though the goods were delivered on 2 January 2020 and agreed to settle the amount within 30 days after the invoice date under the usual credit terms granted to the customer. Since this is a major customer with a good track record, WT Limited entertained the request and issued the invoice to the customer on 31 December 2019. The goods were delivered to the customer on 2 January 2020.

Required: Determine whether the above transaction of WT Limited should be accounted for in the year 2019 in term of revenue recognition.

Part B

Pacific Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2019 and completed in 2020. Cost and other data are presented below:

2019 2020

Costs incurred during the year $450,000 $1,100,000

Estimated costs to complete 1,050,000 0

Billings during the year 400,000 1,400,000

Cash collections during the year 300,000 1,500,000

Assume that Pacific recognizes revenue on this contract over time according to percentage of completion based on cost.

Required:

(a) According to the main theme of IFRS 15, explain the differences between contract assets, and contract liabilities.

(b) Calculate the following amounts in each of the 2019 and 2020.

(i) Total estimated profit of the contract (ii) Gross profit to be recognized for the year

(c) Prepare all necessary journal entries for the year 2020 in relation to the following:

(i)To record contract costs (ii)To record progress billings (iii)To record cash collection (iv)To record revenue recognition

Homework Answers

Answer #1

Answer to first question only (since both are unrelated) as per answering guidelines

Under GAAP / IFRS 15, Revenue is recognized when the Control of goods is passed which can be either over time or at a point in time.

In the extant case since the goods sold were still under the control of WT Limited on the last day of the year ended 2019 which means it had the ability to prevent others from directing the use of and obtaining the benefits from the asset, Hence the control was not passed on till the last day of the year ended 2019. Hence revenue should not be recognized in 2019.

The goods were delivered to the customer on 2 January 2020, hence the control passed on 2 January 2020, hence revenue should be recognized in 2010.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it...
On December 31, 2019, Shawshank Construction Inc. signs a contract to manufacture a bridge which it anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project: Contract price: $780 million Estimated construction costs: $600 million Estimated total profit: $180 million During the three-year construction period, Shawshank incurred costs as follows: 2020 $ 60 million 2021 $360 million 2022 $180 million Shawshank uses the cost-to-cost method to recognize revenue. Which of the...
On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department...
On December 31, 2019, Mass Construction Inc. signs a contract with the state of Massachusetts Department of Transportation to manufacture a bridge over the Merrimack. Mass Construction anticipates the construction will take three years. The company's accountants provide the following contract details relating to the project: Contract price $520 million Estimated construction costs $300 million Estimated total profit $220 million During the three-year construction period, Tri-State incurred costs as follows: 2020 $ 60 million 2021 $150 million 2022 $ 90...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
On December 31, 2019, Coronado Inc. borrowed $4,260,000 at 12% payable annually to finance the construction...
On December 31, 2019, Coronado Inc. borrowed $4,260,000 at 12% payable annually to finance the construction of a new building. In 2020, the company made the following expenditures related to this building: March 1, $511,200; June 1, $852,000; July 1, $2,130,000; December 1, $2,130,000. The building was completed in February 2021. Additional information is provided as follows. 1. Other debt outstanding 10-year, 13% bond, December 31, 2013, interest payable annually $5,680,000 6-year, 10% note, dated December 31, 2017, interest payable...
On December 31, 2019, Culver Inc. borrowed $4,320,000 at 13% payable annually to finance the construction...
On December 31, 2019, Culver Inc. borrowed $4,320,000 at 13% payable annually to finance the construction of a new building. In 2020, the company made the following expenditures related to this building: March 1, $518,400; June 1, $864,000; July 1, $2,160,000; December 1, $2,160,000. The building was completed in February 2021. Additional information is provided as follows. 1. Other debt outstanding 10-year, 14% bond, December 31, 2013, interest payable annually $5,760,000 6-year, 11% note, dated December 31, 2017, interest payable...
On December 31, 2019, Sheffield Inc. borrowed $3,240,000 at 13% payable annually to finance the construction...
On December 31, 2019, Sheffield Inc. borrowed $3,240,000 at 13% payable annually to finance the construction of a new building. In 2020, the company made the following expenditures related to this building: March 1, $388,800; June 1, $648,000; July 1, $1,620,000; December 1, $1,620,000. The building was completed in February 2021. Additional information is provided as follows. 1. Other debt outstanding 10-year, 14% bond, December 31, 2013, interest payable annually $4,320,000 6-year, 11% note, dated December 31, 2017, interest payable...
On December 31, 2019, Sandhill Inc. borrowed $3,060,000 at 13% payable annually to finance the construction...
On December 31, 2019, Sandhill Inc. borrowed $3,060,000 at 13% payable annually to finance the construction of a new building. In 2020, the company made the following expenditures related to this building: March 1, $367,200; June 1, $612,000; July 1, $1,530,000; December 1, $1,530,000. The building was completed in February 2021. Additional information is provided as follows. 1. Other debt outstanding 10-year, 14% bond, December 31, 2013, interest payable annually $4,080,000 6-year, 11% note, dated December 31, 2017, interest payable...
On December 31, 2019, Ayayai Inc. borrowed $3,720,000 at 13% payable annually to finance the construction...
On December 31, 2019, Ayayai Inc. borrowed $3,720,000 at 13% payable annually to finance the construction of a new building. In 2020, the company made the following expenditures related to this building: March 1, $446,400; June 1, $744,000; July 1, $1,860,000; December 1, $1,860,000. The building was completed in February 2021. Additional information is provided as follows. 1. Other debt outstanding 10-year, 14% bond, December 31, 2013, interest payable annually $4,960,000 6-year, 11% note, dated December 31, 2017, interest payable...
10-08 On December 31, 2019, Sheffield Inc. borrowed $4,200,000 at 13% payable annually to finance the...
10-08 On December 31, 2019, Sheffield Inc. borrowed $4,200,000 at 13% payable annually to finance the construction of a new building. In 2020, the company made the following expenditures related to this building: March 1, $504,000; June 1, $840,000; July 1, $2,100,000; December 1, $2,100,000. The building was completed in February 2021. Additional information is provided as follows. 1. Other debt outstanding 10-year, 14% bond, December 31, 2013, interest payable annually $5,600,000 6-year, 11% note, dated December 31, 2017, interest...
Exercise 10-08 On December 31, 2019, Blue Inc. borrowed $4,260,000 at 12% payable annually to finance...
Exercise 10-08 On December 31, 2019, Blue Inc. borrowed $4,260,000 at 12% payable annually to finance the construction of a new building. In 2020, the company made the following expenditures related to this building: March 1, $511,200; June 1, $852,000; July 1, $2,130,000; December 1, $2,130,000. The building was completed in February 2021. Additional information is provided as follows. 1. Other debt outstanding 10-year, 13% bond, December 31, 2013, interest payable annually $5,680,000 6-year, 10% note, dated December 31, 2017,...