Question

On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building....

On June 15, 2020, Lion Construction signed a $ 360,000 contract to build a small building. Lion estimated that the total cost would be $ 320,000. Construction started immediately because the required completion date was August 31, 2021. Lion’s relevant data relating to this construction project were as follows:

     2020             2021

Actual costs incurred $ 120,000      $ 204,000

Estimated costs to complete 200,000               -0-

Progress billings 112,000        248,000

Collections 110,000        250,000

Instructions (show all supporting calculations)

Calculate how much gross profit that Lion should recognize each year, assuming:

       Method Used For 2020            For 2021

a) Completed contract

b) Percentage-of-completion

Homework Answers

Answer #1

Calculate gross profit : Completed contract

2020 2021
Revenue 0 360000
Cost 0 120000+204000 = -324000
Gross profit 0 36000

Calculate gross profit: Percentage completion

2020 2021
Actual costs incurred 120000 204000
Estimated cost to complete 200000 0
Percentage completed 37.50% 100%
Revenue recognized 135000 360000
Actual cost -120000 -324000
Gross profit 15000 36000
In previous year 0 -15000
Gross profit Current year 15000 21000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The...
In February 2020, Sandhill Construction signed a contract and commenced construction on a parking garage. The total contract price was $90.4 million and was expected to be completed in July 2022 at a total estimated cost of $82.4 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily...
On June 1, 2020, Roman Construction Company Inc. contracted to build an office building for Sicily Corp. for a total contract price of $2,600,000. On July 1, Roman estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Sicily 2020, 2021, and 2022. 2020 2021 2022 Costs incurred to date $600,000...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of $5,820,000. Bramble estimated total construction costs would be $4,016,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date. $1,506,000 $2,652,000 $4,610,000 Estimated costs to complete. 2,510,000 1,768,000 -0- Customer billings to date 2,220,000 4,016,000 5,620,000 Collections to date 2,020,000 3,520,000 5,520,000 Fill in the...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $40,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          18,000         28,000 Collections to date                     5,000           15,000         26,000 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is___________________________ .
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract...
Novak Construction Company uses the percentage-of-completion method of accounting. In 2020, Novak began work under contract #E2-D2, which provided for a contract price of $2,170,000. Other details follow: 2020 2021 Costs incurred during the year $615,810 $1,422,000 Estimated costs to complete, as of December 31 963,190 –0– Billings during the year 426,000 2,170,000 Collections during the year 343,000 1,520,000 (a) New attempt is in progress. Some of the new entries may impact the last attempt grading.Your answer is incorrect. What...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Correct answer iconYour answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract...
Wildhorse Construction Company uses the percentage-of-completion method of accounting. In 2020, Wildhorse began work under contract #E2-D2, which provided for a contract price of $2,165,000. Other details follow: 2020 2021 Costs incurred during the year $590,520 $1,409,000 Estimated costs to complete, as of December 31 1,005,480 –0– Billings during the year 428,000 2,165,000 Collections during the year 349,000 1,509,000 What portion of the total contract price would be recognized as revenue in 2020? In 2021? Revenue recognized in 2020 $...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT