Question

When looking at the life of a project plan, it is useful to graph and outline...

When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. Execise#2: 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51? Complete exercise 2 Given the data provided, in an excel spreadsheet, PowerPoint, or other appropriate method of delivery, determine the following: 1. Schedule Variance (SV) 2. Cost Variance (CV) 3. Schedule Performance Index (SPI) 4. Cost Performance Index (CPI) In 250-300 words, answer the questions provided with the exercise. Reflect on the assessment of this project assessment. Should the project continue to improve?

Homework Answers

Answer #1

since SV value is positive. Positive number indicates work that was not suppose to be done by this time has been accomplished.

CV with negative value indicates over budget.

CPI value with less than 1 indicates a cost overrun. A value greater than 1 indicates cost savings. CPI = .92 means we are only earning 92 percents of planned work for each dollar spent.

SPI value less than 1 indicates that work on the project is behind schedule. A value greater than 1 indicates work on the ahead of schedule. SPI = 1.07 means $1.07 worth of work has been accomplished for each $1 worth of scheduled work.

Efforts can be made to reduce CV as it is over budget.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation....
Using the model proposed by Lafley and Charan, analyze how Apigee was able to drive innovation. case:    W17400 APIGEE: PEOPLE MANAGEMENT PRACTICES AND THE CHALLENGE OF GROWTH Ranjeet Nambudiri, S. Ramnarayan, and Catherine Xavier wrote this case solely to provide material for class discussion. The authors do not intend to illustrate either effective or ineffective handling of a managerial situation. The authors may have disguised certain names and other identifying information to protect confidentiality. This publication may not be...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how...
Delta airlines case study Global strategy. Describe the current global strategy and provide evidence about how the firms resources incompetencies support the given pressures regarding costs and local responsiveness. Describe entry modes have they usually used, and whether they are appropriate for the given strategy. Any key issues in their global strategy? casestudy: Atlanta, June 17, 2014. Sea of Delta employees and their families swarmed between food trucks, amusement park booths, and entertainment venues that were scattered throughout what would...