Question

1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...

1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI

a. First, map each description to an EVA category. Then, fill in the table.

Week AC PV EV CV CPI SV SPI
2 72,000

b. What do the SPI and CPI values mean in this example? Explain in "plain English."

c. Could a project or task be where we expect in terms of cost, but behind on schedule? (Hint: see formulas)

2.) You are managing a project to film 5 promotional videos to be posted on YouTube, to promote one of the UI fraternities. Your project jas a BAC of $12,000. One of the tasks on the the critical path is to arrange fililming locations. The task has a BAC of $2,000. You have confirmed 4 of the 10 locations. The task is scheduled to take 2 weeks(10 days), and it is the end of day 2. You have spent $300 so far.

a. Identify the task's BAC, AC, EV and PV

b. Calculate SPI and CPI

c. What do the results tell you about the task's schedule and budget?

3.) You are manging a construction project with a BAC of $1,400,000. You have built 4 of the 5 houses, and you have just finished week 6 on the project, out of the scheduled 11 weeks. Your actual cost has been $800,000 so far. Determine the estimate to complete (ETC) the project, and briefly explain what the result means.

4.) You are managing a task on the critical path which has a BAC of $500,000. The task is 80 percent complete. The team has completed 10 weeks on the task, and it was scheduled to take 10 weeks. You have spent $400,000 on the task so far. Calculate the cost performance index (CPI) and schedule performance index (SPI). Briefly explain what the reults mean.

Homework Answers

Answer #1

1.

a. First, map each description to an EVA category. Then, fill in the table.
PC Percentage complete 70% (7/10)
TC Total budgeted cost 100000
EC Expected completion 66.7% (2/3)
Earned value= (7/10)
PC*TC EC*TC EV-AC EV/AC EV-PV EV/PV
Week AC PV EV CV CPI SV SPI
2 72,000 70000 66666.6667 -5,333 0.92592593 -3333.33333 0.95238095
Planned or budgeted
b. What do the SPI and CPI values mean in this example? Explain in "plain English."
As CPI is less than one the actual costs have been more than the work completed and SPI suggests the project is behind the planned progress.
c. Could a project or task be where we expect in terms of cost, but behind on schedule? (Hint: see formulas)
As the SV is negative the project is behind schedule.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are managing a project to film 5 promotional videos to be posted on youtube. Your...
You are managing a project to film 5 promotional videos to be posted on youtube. Your project has a BAC of $12,000. One of the tasks on the critcal path is to arrange filming locations. The task has a BAC of $2,000. You have confirmed 4 of the 10 locations. The task is scheduled to take 2 weeks (10 days), and it is the end of day 2. You have spent $300 so far. A) identify the tasks BAC, AC,...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
The PM for the web project left and you have been assigned to manage the project....
The PM for the web project left and you have been assigned to manage the project. The PERT for this project is 30 days and the variance is +/-5 days. There are too many activities on the critical path. The Early Start for task A on the critical path is day 5 and the Late Start is day 7, the Early Finish is day 10, and the Late Finish is on day 15. The CPI is 0.5, but the SPI...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative...
London Fletcher of Fabriscan Diagnostic, is the project manager. He measured the following information with commutative completed times for four periods of the project. Completed% Activity ID Activity Predecessors Estimated Duration(Weeks) Budget ($) Actual Spend ($) 1 2 3 4 Crash time Crash cost$ A 7          7,000                       9,000 20 40 100 100 6             8,000 B A 2          5,000                       5,000 20 60 100 100 1             7,000 C A 4          9,000                       6,000 0 40...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Financial information for the project: 1. You decide to open a small business in Charleston, WV...
Financial information for the project: 1. You decide to open a small business in Charleston, WV that will cater primarily to busy office workers downtown. You are going to offer a gourmet box lunch to be delivered to any office with a minimum number of 5 orders. This lunch will include a gourmet sandwich, a bag of chips, a cookie, and a bottle of water. Because you are using only the finest ingredients, you will charge $9.15per lunch. 2. The...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...