Question

Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...

Part 1 a)

Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value):

The data identified below was listed in a project’s status report.

At time of status report:

Planned Value of work (PV) = $70,000

Earned Value of work performed (EV) = $50,000

Actual Cost of work performed (AC) = $75,000

Original Planning:

Budgeted cost At Completion (BAC) = $110,000

Original length of the project is 15 months

Using the data, calculate the following:

a)    Cost Performance Index (CPI). (1 mark)

b) Schedule Performance Index (SPI). (1 mark)

c)      Expected cost At Completion (EAC). (1 mark)

d) Estimate To Complete (ETC).

e) The Schedule Variance (SV).

f) Discuss how the project is tracking (e.g. ahead or behind schedule, under or over budget)?

Answer a) through f) in one text box below:

Homework Answers

Answer #1

Answer here

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
EV= 30,000 , PV= 40,000 , AC= 45,000 , CPI= 0.667 , SPI= 0.75 Budgeted value=...
EV= 30,000 , PV= 40,000 , AC= 45,000 , CPI= 0.667 , SPI= 0.75 Budgeted value= 50,000 Calculate the following: 1. Using the above EV, AC, and BAC to calculate the estimate at completion value for estimated to complete work performed at the budgeted rate. EAC = 2. Using the above EV, AC, BAC, and CPI calculate the estimate at completion value for estimated to complete work performed at the present CPI. EAC = 3. Using the above EV, AC,...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
When looking at the life of a project plan, it is useful to graph and outline...
When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. Execise#2: 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day...
EVM For the previous problem, assume that you are at the end of day 5, activity...
EVM For the previous problem, assume that you are at the end of day 5, activity 10 is 100 percent complete, activity 20 is 66.6 percent complete, and activity 30 is 80 percent complete. Actual costs: Activity 10: $2,000 Activity 20: $900 Activity 30: $1,800 Please answer the following questions. How is the Project Doing? (0.5 point each) ACWP: BCWS: BCWP: Schedule Variance: SPI: Cost Variance: CPI: Assessment (1 point): What do we expect the costs to be at completion?...
The Schedule Performance Index relies on________________ and __________________. earned value       forecasted value earned value       planned value...
The Schedule Performance Index relies on________________ and __________________. earned value       forecasted value earned value       planned value earned value       actual value None of the above Value Engineering (VE) is aimed at _____________________. identifying areas of a project where money and resources can be saved determining the value of a project All of the above determining the best value of a project One of the components of the Cost Management Plan is _______________________. the level of accuracy of estimating the project’s cost...
part 1) The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and...
part 1) The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and is the budgeted or estimated cost for each of the tasks in the schedule that should have been completed or partially completed as of the date of selected. Group of answer choices true false part 2 Cost Performance Index (CPI) can be used a tool to project the total estimated project cost at completion. If a project's original estimate (budget) was $2,400,500 and the...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000. Compute the following for the project (10 points) a) Cost variance. b) Schedule variance. c) If rest of the project is assumed...