Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value):
The data identified below was listed in a project’s status report.
At time of status report:
Planned Value of work (PV) = $70,000
Earned Value of work performed (EV) = $50,000
Actual Cost of work performed (AC) = $75,000
Original Planning:
Budgeted cost At Completion (BAC) = $110,000
Original length of the project is 15 months
Using the data, calculate the following:
a) Cost Performance Index (CPI). (1 mark)
b) Schedule Performance Index (SPI). (1 mark)
c) Expected cost At Completion (EAC). (1 mark)
d) Estimate To Complete (ETC).
e) The Schedule Variance (SV).
f) Discuss how the project is tracking (e.g. ahead or behind schedule, under or over budget)?
a) Cost Performance Index (CPI) = EV / AC
= 50,000 / 75,000
CPI = 2 / 3
b) Schedule Performance Index (SPI) = EV / PV
= 50,000 / 70,000
SPI = 5 / 7
c) Expected cost At Completion (EAC) = BAC / CPI
= 110,000 / (2/3)
EAC = $165,000
d) Estimate To Complete (ETC) = Supposed Time / SPI
= 15 / (5/7)
ETC = 21 months
e) The Schedule Variance (SV) = EV - PV
= 50,000 - 70,000
SV = $-20,000
f) CPI = 2/3 (less than one) means Over-Budget
SPI = 5/7 (less than one) means Behind Schedule
Over Budget and Behind Schedule
Get Answers For Free
Most questions answered within 1 hours.