Question

Line balancing: With considering the following tasks: task number avg. performance time number of successors 1...

Line balancing:

With considering the following tasks:

task number avg. performance time number of successors
1 5 7
2 3 6
3 6 4
4 8 5
5 10 3
6 7 3
7 1 2
8 5 0
9 3 0

  

a. Estimate the cycle time to reach minimum idle time and end up having 4 workstations.  

b. Imagine the considered cycle time is 17. Which of the following methods gives us the best solution? Why? (you need to compare the solutions numerically).

o Largest‐candidate rule   

o Kilbridge and Webster’s method   

o Line of Balance (LOB)  

o Ranked positional weight  

Homework Answers

Answer #1

We have ,Number of workstations N=Sum of task times/Cycle time

therefore ,Cycletime =Sum of task times/N

From the given data, Sum of task times =48

Cycle time =48/4 =12

b. Given cycle time =17

a. Longest candidate rule

b.Kilbridge and Webster's method

Ranked positional weight

All the above three methods have same number of workstations =4

Efficiency =Sum of task times/(number of work stations * cycle time) =70.58 %

Line of Balance :

Tc =17

Tr =repositioning time for movement of the product from one station to next.

Assume Tr =0.7

Ts=Tc-Tr=17-0.7 =16.3

Line efficiency =Sum of task times/(number of work stations *Ts) =48/4*16.3=73.61 %

So,the line of Balance method gives higher efficiency than the rest of the methods and hence is the best method.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 120 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C...
TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec D Meat -B 10 sec E Salsa -C, D 10 sec F Cheese -E 5 sec G Sour Cream -E 10 sec H Lettuce -E 10 sec I Wrap -F, G, H 15 sec J Bag -I 5 sec K Checkout/pay -J 25 sec Achieving the above cycle time and output, what is the theoretical number of workstations? Assign tasks...
Element No. Task Time Must be preceded by (min) 1 0.3 - 2 0.2 1 3...
Element No. Task Time Must be preceded by (min) 1 0.3 - 2 0.2 1 3 0.6 - 4 0.2 3 5 0.5 4 6 0.21 2 7 0.45 5,6 8 0.9 5 9 0.32 7 10 0.1 8,9 11 0.8 10 12 0.6 11 The desired cycle time is 1.2 min. (a) generate a an Assembly Line Balance system with stations and work elements allocated to each of the stations. (b) If cycle time is readjusted to maximum of...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar chests, the length of time needed to perform each task, and the operations that must be complete prior to subsequent operations are given below. With a production quota of 300 units in a 35 hour week, the desired cycle time is closest to ______. Element Time (min) Predecessors A 2 NONE B 3 A C 5 B D 5 NONE E 4 D F...
Suppose you are given a set S = {a1,a2,···,an} of tasks, where task ai requires pi...
Suppose you are given a set S = {a1,a2,···,an} of tasks, where task ai requires pi units of processing time to complete, once it has started. You have one computer on which to run these tasks, and the computer can run only one task at a time. Let ci be the completion time of task ai, that is, the time at which task ai completes processing. Your goal is to minimize the average completion time, that is, to minimize n1...
Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers...
Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers performing these tasks seven times, with the results (in minutes) shown in the following table. No Tasks 1 2 3 4 5 6 7 PR 1 Select correct mufflers 6 4 3 4 5 4 4 100 2 Remove old muffler 8 8 8 8 7 7 5 110 3 Install new muffler 11 11 11 14 13 14 13 85 4 Inspect the...
Complete this table. Which tasks have the highest degree of uncertainty in terms of the time...
Complete this table. Which tasks have the highest degree of uncertainty in terms of the time required to complete them? Please provide a detailed explanation (Specifically the formula used in column "T & Standard Deviation") Task To (optimistic) Tm (most likely) Tp (pessimistic) T Standard Deviation Predecessor Task 1 3 days 7 days 14 days 0 2 16 days 21 days 43 days 1 3 6 days 8 days 15 days 2 4 9 days 11 days 19 days 2...
Work standards specify time, cost, and efficiency norms for the performance of work tasks. They are...
Work standards specify time, cost, and efficiency norms for the performance of work tasks. They are typically used to monitor job performance. In the distribution center of McCormick and Co., Inc., data were collected to develop work standards for the time to assemble or fill customer orders. The table below contains data for a random sample of 9 orders. x is the number of cases in the order and y is the time used. Note: sum x = 1149, sum...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8...
The pizza-making process at Mama’s is outlined in the table below. The shop is open 8 hours a day to fulfill a typical daily demand of 40 pizzas. Sketch the process and balance the assembly to answer the questions below. Task Predecessor Minutes A. Roll Dough -- 12 B. Spread Sauce A 4 C. Prepare Toppings -- 7 D. Put Toppings on Pizza B,C 3 E. Sprinkle Cheese D 2 F. Bake Pizza E 10 1. What is the maximum...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT