Question

Complete this table. Which tasks have the highest degree of uncertainty in terms of the time...

Complete this table. Which tasks have the highest degree of uncertainty in terms of the time required to complete them?

Please provide a detailed explanation (Specifically the formula used in column "T & Standard Deviation")

Task

To

(optimistic)

Tm

(most likely)

Tp

(pessimistic)

T

Standard Deviation

Predecessor Task

1

3 days

7 days

14 days

0

2

16 days

21 days

43 days

1

3

6 days

8 days

15 days

2

4

9 days

11 days

19 days

2

5

18 days

21 days

38 days

2, 3

6

13 days

18 days

30 days

5

7

12 days

17 days

27 days

6

8

7 days

9 days

13 days

6, 7

Homework Answers

Answer #1

please like.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers...
Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers performing these tasks seven times, with the results (in minutes) shown in the following table. No Tasks 1 2 3 4 5 6 7 PR 1 Select correct mufflers 6 4 3 4 5 4 4 100 2 Remove old muffler 8 8 8 8 7 7 5 110 3 Install new muffler 11 11 11 14 13 14 13 85 4 Inspect the...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
Part A. In the past it has been found that the arrival time have a population...
Part A. In the past it has been found that the arrival time have a population mean value of μ = 13 and a population standard deviation of σ = 6.26. Using the given data, test whether this mean has changed. Use the critical value approach to test the hypothesis. The significance level alpha is set at 0.05 . The original data of time taken is given below. Show the process by using excel (Formulas). Part B. Test the hypothesis...
Path Activity to tm tp te=(to+4tm+tp)/6 Path total A-C-F-H A 3 4 5 4 19 C...
Path Activity to tm tp te=(to+4tm+tp)/6 Path total A-C-F-H A 3 4 5 4 19 C 2 3 10 4 F 3 5 7 5 H 2 6 10 6 B-D-F-H B 5 7 9 7 23 D 2 5 8 5 F 3 5 7 5 H 2 6 10 6 B-E-G B 5 7 9 7 21 E 1 7 7 6 G 7 8 9 8 The critical path is B-D-F-H. Hence, the expected duration of project...
Find the critical path and the project completion time for the following list of activities. Calculate...
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in: a) 13 days or more b) 11 days or less c) Between 12 and 14 days Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration A - 1 3 5 B - 2 4 6 C A,B 2 4 5 D A,B 3 5 7 E C,D 1 2 10 I do not understand how...
A computer scientist is investigating the usefulness of two different design languages in improving programming tasks....
A computer scientist is investigating the usefulness of two different design languages in improving programming tasks. Twelve expert programmers, familiar with both languages, are asked to code a standard function in both languages, and the time (in minutes) is recorded. The data follow: Programmer Time Design Language 1 Design Language 2 1 17 18 2 17 14 3 21 20 4 14 11 5 18 23 6 24 21 7 15 10 8 14 13 9 21 19 10 23...
A future construction project has the following activity relationships and activity time estimates (in days): Activity...
A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm Tp A None 4 5 6 B None 3 6 21 C B 1 4 7 D A 2 5 8 E C, D 3 9 27 F C 3 6 15 G E, F 2 4 6 H F, G 2 2 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Assuming that the population standard deviation is unknown, calculate the 95% confidence interval of the population...
Assuming that the population standard deviation is unknown, calculate the 95% confidence interval of the population mean. The following is the data. Calculating Process should be shown by Excel (Formulas). What formulas in statistics are used? 7 21 23 24 18 16 2 19 11 6 3 13 17 9 5 12 13 17 4 14 15 25 12 24 22 14 14 20 15 11 26 17 21 11 4 13 16 14 13 14 25 23 9 15...