Complete this table. Which tasks have the highest degree of uncertainty in terms of the time required to complete them?
Please provide a detailed explanation (Specifically the formula used in column "T & Standard Deviation")
Task |
To (optimistic) |
Tm (most likely) |
Tp (pessimistic) |
T |
Standard Deviation |
Predecessor Task |
1 |
3 days |
7 days |
14 days |
0 |
||
2 |
16 days |
21 days |
43 days |
1 |
||
3 |
6 days |
8 days |
15 days |
2 |
||
4 |
9 days |
11 days |
19 days |
2 |
||
5 |
18 days |
21 days |
38 days |
2, 3 |
||
6 |
13 days |
18 days |
30 days |
5 |
||
7 |
12 days |
17 days |
27 days |
6 |
||
8 |
7 days |
9 days |
13 days |
6, 7 |