Question

There are seven tasks in an assembly line, from which a product with a relative stable...

There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently way possible.

  • A (5) ----> B (3) ----> D (1) ----> E (1) -----> F (2) ------> G(4)
  • C (2)------------------>
  1. What is the desired cycle time (in minutes) of the balanced assembly line? (Keep two decimals if not exact, do not round. For example, 3.24923... will be kept as 3.24)  
  2. Assumed the desired cycle time is 5 minutes, please used the assumed CT value to calculate the minimum number of workstations needed (round up to an integer number) for line-balancing, in order to achieve the best process efficiency.  
  3. Assumed the desired cycle time is 5 minutes, please used the assumed CT value to balance the assembly line using the greatest positional weight rule. Which tasks would be assigned to the last workstation? (Letter only, NO space or comma between letters, e.g., ABDE)

Homework Answers

Answer #1

Desired cycle time = available time/desired output = (8*60)/100 = 4.8 minutes

using the assumed minimum number of workstations needed = sum of task times/assumed cycle time = (5+3+2+1+1+2+4)/5 = 3.6 = 4(Rounded to integer)

Activity Positional weight
A 16
B 11
C 10
D 8
E 7
F 6
G 4

Balanced assembly line

Workstation Eligible task Assigned task Task time Idle time remaining
I A,C A 5 0
II B,C B 3 2
C C 2 0
III D D 1 4
E E 1 3
F F 2 1
IV G G 4 1

Task G would be assigned to the last workstation

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 120 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
Line balancing: With considering the following tasks: task number avg. performance time number of successors 1...
Line balancing: With considering the following tasks: task number avg. performance time number of successors 1 5 7 2 3 6 3 6 4 4 8 5 5 10 3 6 7 3 7 1 2 8 5 0 9 3 0    a. Estimate the cycle time to reach minimum idle time and end up having 4 workstations.   b. Imagine the considered cycle time is 17. Which of the following methods gives us the best solution? Why? (you need...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar chests, the length of time needed to perform each task, and the operations that must be complete prior to subsequent operations are given below. With a production quota of 300 units in a 35 hour week, the desired cycle time is closest to ______. Element Time (min) Predecessors A 2 NONE B 3 A C 5 B D 5 NONE E 4 D F...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: Task Time (seconds) Predecessors A 10 – B 33 A C 23 A D 24 C,B E 20 D F 18 D G 36 E,F b. What is the takt time? (Round your answer to the nearest whole number.) c. What is the theoretical number of workstations? (Round up...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a...
The following process tasks, elemental times and precedence relationships are given. Initially, the company expects a forecasted demand of 50 units/hour. Find an assembly line that will produce the necessary output. Task Time (in seconds) Immediate Predecessor A 55 - B 30 A C 35 A D 22 B E 50 B,C F 15 C G 5 F H 10 G Part 2. Complete this exercise again, but this time the company expects a forecasted demand of 20 units/hour. Find...
Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton,...
Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton, Illinois. Recently hired general manager, Bob Behar, is concerned about the large inventories and manufacturing inefficiencies in the plant. The Paxton plant has two separate assembly lines – one for chairs and one for tables. Demand for chairs is significantly larger than tables, so Bob decides to tackle the table assembly process for first. Bob has recently hired a summer intern, Eileen Mayer, who...
How can differential analysis be applied here to determine if it would be profitable to invest...
How can differential analysis be applied here to determine if it would be profitable to invest in new equipment to increase capacity for a constrained resource? KRAYDEN’S CYCLE COMPONENTS INTRODUCTION: COMPANY, PRODUCT, AND SUPPLY CHAIN Krayden’s Cycle Components (KCC) is a high-end specialty fabricator that manufactures one product with many variants. The basic product is known as a rolling chassis, a key component used in manufacturing motorcycles. While there are variations across the industry, a rolling chassis typically consists of...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...
CASE STUDY - LG Electronics From its origins as the progenitor of South Korea’s electronics industry...
CASE STUDY - LG Electronics From its origins as the progenitor of South Korea’s electronics industry and then its first global exporter, LG Electronics has evolved to a respected global brand with manufacturing facilities in China, India, Mexico, Brazil, Poland, and Russia and a presence in 49 countries. Headquartered in Seoul, South Korea, the company has 84,000 employees in 112 locations around the world, including 81 subsidiaries. Perhaps best known today for its quality mobile phones, LG Electronics is also...
Sign In INNOVATION Deep Change: How Operational Innovation Can Transform Your Company by Michael Hammer From...
Sign In INNOVATION Deep Change: How Operational Innovation Can Transform Your Company by Michael Hammer From the April 2004 Issue Save Share 8.95 In 1991, Progressive Insurance, an automobile insurer based in Mayfield Village, Ohio, had approximately $1.3 billion in sales. By 2002, that figure had grown to $9.5 billion. What fashionable strategies did Progressive employ to achieve sevenfold growth in just over a decade? Was it positioned in a high-growth industry? Hardly. Auto insurance is a mature, 100-year-old industry...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT