Element No. | Task Time | Must be preceded by | |||||
(min) | |||||||
1 | 0.3 | - | |||||
2 | 0.2 | 1 | |||||
3 | 0.6 | - | |||||
4 | 0.2 | 3 | |||||
5 | 0.5 | 4 | |||||
6 | 0.21 | 2 | |||||
7 | 0.45 | 5,6 | |||||
8 | 0.9 | 5 | |||||
9 | 0.32 | 7 | |||||
10 | 0.1 | 8,9 | |||||
11 | 0.8 | 10 | |||||
12 | 0.6 | 11 | |||||
The desired cycle time is 1.2 min. | |||||||
(a) | generate a an Assembly Line Balance system with stations and work elements | ||||||
allocated to each of the stations. | |||||||
(b) | If cycle time is readjusted to maximum of station times, what is the cycle time? | ||||||
( c) | For the cycle time in (b), compute the line efficiency. |