Question

What do the following mean in project management: -positive expenditure variance? -negative schedule variance? -negative cost...

What do the following mean in project management:

-positive expenditure variance?

-negative schedule variance?

-negative cost variance?

positive/negative

Homework Answers

Answer #1

Positive expenditure variance means that the expense is less than the budgeted amount. Having a positive expenditure variance is a good thing.

Schedule variance tells us whether the project is ahead or behind the time schedule. A negative schedule variance means that the project is behind the planned time schedule.

Negative cost variance means that the expense or cost of the project is more than the budgeted amount. Having a negative cost variance is a bad thing.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Consider the following statement: “The essence of project management is risk management.” What does it mean...
Consider the following statement: “The essence of project management is risk management.” What does it mean in terms of completing a project successfully? Support your response with evidence from the readings or other materials. Be sure to cite your source.
Compare and Contrast positive and negative correlation. What do positive and negative correlations say about the...
Compare and Contrast positive and negative correlation. What do positive and negative correlations say about the relationship between two variables?
Compare and Contrast positive and negative correlation. What do positive and negative correlations say about the...
Compare and Contrast positive and negative correlation. What do positive and negative correlations say about the relationship between two variables?
subject,,,,,project management.. All projects have a level of uncertainty. The project manager should do whatever possible...
subject,,,,,project management.. All projects have a level of uncertainty. The project manager should do whatever possible to identify the risks that can affect the project. How can technology be a risk to the project? Is it positive or negative in nature?
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
What is a postive affect and negative affect when it come to PANAS (The positive and...
What is a postive affect and negative affect when it come to PANAS (The positive and negative affect schedule scale)? So I'm in a research where I use STATISTICS to do a paired T-Test on Drug Negative Affect Vs Placebo Negative Affect as well as Drug Positive Affect vs Placebo Positive Affect (This is a state scale not a trait) . I'm not sure how you would distinguish between the positive and negative affect PANAS. So is this basically one...
What can organizations do to ensure that estimates are good (ie: Project Management Projects)? What can...
What can organizations do to ensure that estimates are good (ie: Project Management Projects)? What can they do to prevent cost overruns?
Shareholders would want management to invest in a negative NPV project only when Group of answer...
Shareholders would want management to invest in a negative NPV project only when Group of answer choices A) The project is low risk and the company has substantial debt in its capital structure. B) The project is low risk and the company has no debt in its capital structure. C) The project is high risk and the company has substantial debt in its capital structure. D) The project is high risk and the company has no debt in its capital...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT