Question

While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging...

While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging in the market. In response, the management at Fabric Mills quickly bumped up the regular output of medical-grade fabric by reassigning workers from the production of regular fabric and rehiring retired workers. Table 2 shows the demand forecast and capacity for medical-grade fabric. Note that overtime is limited to 20% of the regular capacity. The availability of subcontract is also limited due to the capacity shortage worldwide.

Table 2: Demand Forecast and Capacity for Medical-Grade Fabric (in Hundreds of Bolts)

Month

5

6

7

8

9

10

11

Forecast

300

300

300

200

200

100

100

Regular Capacity

200

200

200

150

150

150

150

Overtime

40

40

40

30

30

30

30

Subcontract

50

50

50

50

50

50

50

The table below summarizes the cost information for medical-grade fabric.

Regular output

$80 per hundred bolts

Overtime

$120 per hundred bolts

Subcontract

$100 per hundred bolts

Inventory carrying cost

$10 per hundred bolts

Backlog

$150 per hundred bolts

QUESTION 6

To begin with, Chris assumes that both ending inventory and backlog in Month 4 are zero for simplicity. Under this scenario, develop a chase plan. Backlog is allowed. Which month has the largest amount of backlog?

Hints:

  • Enter “0” in Cell D9 and Cell D11 in the Aggregate Planning worksheet.
  • Use regular output as much as possible to satisfy demand as it’s the most inexpensive option.
  • If demand exceeds regular output, use subcontract next (the second inexpensive option) and then overtime (the least inexpensive option).
  • If there is still unfilled demand, you are allowed to have backlog.
  • Although backlog is allowed, reduce it as much as possible as it’s very expensive.
  • As it’s a chase plan, no inventory should be carried.

  1. Month 5
  2. Month 6
  3. Month 7
  4. None of the above

QUESTION 7

In the chase plan developed in QUESTION 6, how much is the total cost?

  1. $128,000
  2. $140,000
  3. $140,600
  4. $149,000

QUESTION 8

Under the scenario in QUESTION 6, now develop a level plan. Backlog is allowed. How much is the total cost?

Hint:

  • In a level plan, you cannot reduce regular outputs. You need to use all available regular outputs.
  • If regular outputs fall short of demand, use subcontract and overtime (in this order) to fill the gap.

  1. $128,000
  2. $140,000
  3. $140,600
  4. $149,000

QUESTION 9

Chris now considers a different scenario. Given the surging demand for medical-grade fabric, it is likely that there will be unfilled demand in Month 4. He estimates that 100(00) bolts will be backlogged at the end of Month 4. This implies that there is no ending inventory in Month 4. Under this scenario, develop a chase plan. Backlog is allowed. How much is the total cost?

Hints:

  • Enter “0” in Cell D9 and “100” in Cell D11 in the Aggregate Planning worksheet.
  • Also see the hints in QUESTION 6. All the hints, excluding the first one, apply to this question as well.

  1. $210,300
  2. $210,700
  3. $220,100
  4. $220,500

QUESTION 10

Under the scenario in QUESTION 9, develop a level plan. Then, compare its total cost to the total cost in the chase plan developed in QUESTION 9. Which plan has a lower total cost?

  1. The chase plan
  2. The level plan

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Jerusalem Medical? Ltd., an Israeli producer of portable kidney dialysis units and other medical? products, develops...
Jerusalem Medical? Ltd., an Israeli producer of portable kidney dialysis units and other medical? products, develops a? 4-month aggregate plan. Demand and capacity? (in units) are forecast as? follows: ????????????????????????????????????????????????????????????????????????????????????????????????????????????????   Capacity Source Month 1 Month 2 Month 3 Month 4 Labor ??????Regular time 225 275 300 300 ??????Overtime 15 24 26 24 Subcontract 14 15 13 15 Demand 240 314 331 301 The cost of producing each dialysis unit is ?$875 on regular? time, ?$1,310 on? overtime, and ?$1,600 on...
Denver Tire Co. would like to develop a level and chase aggregate plan using the following...
Denver Tire Co. would like to develop a level and chase aggregate plan using the following information: Capacity = 900 tires/mo on regular time;  100 tires/mo on overtime; 150 tires/mo subcontracting. Beginning Inventory = 0 tires; Planned ending inventory = 100 tires. Costs = Regular ($40/tire); Overtime ($50/tire); Subcontracting ($70/tire) Carrying Cost = $2/tire/month;   Backlog cost = $20/tire. a.  Produce a level plan below that minimizes total costs.    Month Mar Apr May Demand 800 1300 800 Total Cost of Level Plan =...
Wormwood, LTD produces a variety of furniture products. The planning committee wants to produce an aggregate...
Wormwood, LTD produces a variety of furniture products. The planning committee wants to produce an aggregate plan for the next 6 months. Complete the spreadsheet cells colored in blue. Month 1 2 3 4 5 6 Demand 160 150 160 180 170 140 Demand Units Capacity Cost Per Unit Regular 150 150 150 150 160 160 Regular Units $50 Max Overtime 10 10 10 10 10 Overtime Units $75 Max Subcontract 10 10 10 10 10 10 Subcontract Units $80...
Week 4 Exercise (Sales & Operations planning) – for 3% of the total grade A small...
Week 4 Exercise (Sales & Operations planning) – for 3% of the total grade A small company produces a variety of recreational and leisure vehicles. The sales & marketing manager has developed the following aggregate forecasts: Month Mar Apr May Jun Jul Aug Sep Forecast 50 44 55 80 70 40 50 Use the following information: Regular labor cost                  $240 per unit Overtime labor cost                $360 per unit Subcontracting cost                $400 per unit Regular capacity                     50 units per month Overtime...
Cornwell Glass produces replacement automobile glass for all makes of cars. Cornwell has a sophisticated forecasting...
Cornwell Glass produces replacement automobile glass for all makes of cars. Cornwell has a sophisticated forecasting system that uses data from past years to find seasonal factors and long-term trends. The system uses data from past weeks to find recent trends. The following table presents the forecasted demands for the coming year on a weekly basis. Week Demand Week Demand April 15 1,829 November 4 1,864 22 1,820 11 1,989 29 1,887 18 2,098 May 6 1,958 25 2,244 13...
What role could the governance of ethics have played if it had been in existence in...
What role could the governance of ethics have played if it had been in existence in the organization? Assess the leadership of Enron from an ethical perspective. THE FALL OF ENRON: A STAKEHOLDER FAILURE Once upon a time, there was a gleaming headquarters office tower in Houston, with a giant tilted "£"' in front, slowly revolving in the Texas sun. The Enron Corporation, which once ranked among the top Fortune 500 companies, collapsed in 2001 under a mountain of debt...
Discuss ethical issues that can be identified in this case and the mode of managing ethics...
Discuss ethical issues that can be identified in this case and the mode of managing ethics Enron finds itself in this case. How would you describe the ethical culture and levels of trust at Enron? Provide reasons for your assessment. THE FALL OF ENRON: A STAKEHOLDER FAILURE Once upon a time, there was a gleaming headquarters office tower in Houston, with a giant tilted "£"' in front, slowly revolving in the Texas sun. The Enron Corporation, which once ranked among...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT