Question

In which phase(s) do you identify project stakeholders? Initiating, Planning, Execution Initiating and Planning Initiating, Planning,...

In which phase(s) do you identify project stakeholders?

Initiating, Planning, Execution

Initiating and Planning

Initiating, Planning, and Monitoring & Controlling

All phases

Your project objective is to replace all of your internal photocopy machines. You have been givien a large set of requirements from the users. Having evaluated solutions from four vendors you realize that not every vendor can satisfy all the requirements. There is some risk involved and you decide to use the Expected Monetary Value (EMV) method to analyze the problem. If you just used EMV, which of the following vendors would you select?

Vendor 1: 80% probability of success and a profit of $20,000

Vendor 2: 90% probability of success and a profit of $19,000

Vendor 3: 75% probability of success and a profit of $18,000

Vendor 4: 85% probability of success and profit of $20,000

Homework Answers

Answer #1

1.

We identify stakeholders in

initiation: Defining the project

Planning: Breaking the project to parts and who will be doing them.

Hence option C

2.

Net EMV = Prob * Profit
Vendor 1: 80% probability of success and a profit of $20,000 16000
Vendor 2: 90% probability of success and a profit of $19,000 17100
Vendor 3: 75% probability of success and a profit of $18,000 13500
Vendor 4: 85% probability of success and profit of $20,000 17000

Hence option B

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning,...
The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.   a)   Which is PMBOK Knowledge area using a tool of Stakeholder Register? b)   Which is PMBOK Knowledge area using a tool of Project Charter? c)      Which are two PMBOK Knowledge areas that use the tool of Resource Levelling? d)      Which are two PMBOK Knowledge areas that...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Project Risk Response Risk responses and action steps are defined during the risk response planning phase....
Project Risk Response Risk responses and action steps are defined during the risk response planning phase. Here the project team must plan the actions that will be taken should any identified risk actually materialize. This is typically done for some subset of the total population of risk issues identified—most likely those that are of the highest probability and/or impact. Risks can be both negative (threats) and positive (opportunities). The possible strategies for responding to negative risks include the following: avoid,...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
Explain the complete HAZOP procedure as followed in the industry. See summary below. Explain all the...
Explain the complete HAZOP procedure as followed in the industry. See summary below. Explain all the main parts of HAZOP study in details given in the Pdf file including: 1. Overview (including definitions and usage) 2. Hazop methodology (including phases like definition, preparation, examination, documentation and follow-up). Give examples also 3. Risk review 4. Risk communication Guidance: Study the procedure carefully and then write the answers in your own words. Hazard & Operability Analysis (HAZOP) 1   Overview: Hazard and Operability...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT