The Project Management Body of Knowledge (PMBOK) recommends five (5) phases/process groups which are Initiating, Planning, Execution, Monitoring and Control; and Closing. There are PMBOK ten (10) Knowledge areas as well as tools associated to them.
a) Which is PMBOK Knowledge area using a tool of Stakeholder Register?
b) Which is PMBOK Knowledge area using a tool of Project Charter?
c) Which are two PMBOK Knowledge areas that use the tool of Resource Levelling?
d) Which are two PMBOK Knowledge areas that use the tool of WBS?
e) Which is PMBOK Knowledge area using the tool of risk register?
Answer a) through e) in one text box below:
Q a) Which is PMBOK Knowledge area using a tool of Stakeholder Register?
Ans: As we all very well aware about how the project’s stakeholders are important .In the Project Management Body of Knowledge (PMBOK) basically the Project Stakeholder Management knowledge are used for the stakeholder register.In the Project Stakeholder Management following processes are done:
Q b) Which is PMBOK Knowledge area using a tool of Project Charter?
Ans: The Project Integration Management knowledge are used a tool of the project charter.In this knowledge area it holds the overall project together and the important thing is that it integrate it into unified whole.And we know in the development of the project charter when one or two processes in the duration of the Initiation phase and the development of the project charter initiates the project and it also authorizes the project manager.
Q c) Which are two PMBOK Knowledge areas that use the tool of Resource Levelling?
Ans: We all very well aware about the project budget , it is basically the most sensitive parts of a project.The two PMBOK Knowledge areas that use the tool of Resource Levelling it make be the following:
Q d) Which are two PMBOK Knowledge areas that use the tool of WBS?
Ans: WBS is basically the Work Breakdown Structure.We know that the WBS basically contains either the graphical or a table-style breakdown of the project work.The two PMBOK Knowledge areas that use the tool of WBS are :
Project Scope Management Knowlege.
Project Time Management knowledge.
Q e) Which is PMBOK Knowledge area using the tool of risk register?
Ans: As we know that in the PMBOK , the the risk register is basically the output of Identify the Risk process in the Risk Management knowledge area. It basically identify the dentify the risks, that could impact on the project and it also understand the nature of those risks.
The Project Risk Management knowledge area uses the tool of risk register .In this it manage the project risk and analyze the project project management plan.
THANKS , i think this will give you a better intuition about your questions. If you have any doubt feel free to ask in the comment section.