Question

Consider the following two projects: Project Year 0 CF Year 1 CF Year 2 CF Year...

Consider the following two projects:

Project

Year 0

CF

Year 1

CF

Year 2

CF

Year 3

CF

Year 4

CF

Cost of capital

A

-100

40

50

60

10

15%

B

-73

30

30

30

30

15%

The IRR of project A =? maybe round this one to the closest?

A) 7.7%

B) 21.6%

C) 23.3%

D) 42.9%

The IRR of project B =?

A) 21.6%

B) 23.3%

C) 42.9%

D) 7.7%

Which of the following statements is correct?

A) Accept project A since its IRR > 15%.

B) Reject project B since its NPV > 0.

C) Accept project A since its NPV < 0.

D) Accept project B since its IRR < 15%.

The maximum number of IRRs that can be found for project B is:

A) 3

B) 1

C) 2

D) 0

The crossover rate is:

A) 27.65%

B) 15.31%

C) 20.58%

D) 33.26%

Homework Answers

Answer #1

Using Excel formula to calculate IRR and Crossover rate

A B C
Year Project A Project B Cash Flow difference
1 0 -100 -73 -27
2 1 40 30 10
3 2 50 30 20
4 3 60 30 30
5 4 10 30 -20
IRR 24.28% 23.34% 27.65% Crossover Rate
Using excel formula IRR(A1:A5) IRR(B1:B5) IRR(C1:C5)

1. First IRR of A is 24.28%
2. IRR of B is 23.34%
3.Option A accept Project Because IRR is greater than 15%
4. Number of IRRs of B is 1
5. Option a crossover rate is 27.65%

Please Discuss in case of Doubt

Best of Luck. God Bless
Please Rate Well

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...
Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4 Discount Rate (%) Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow A -90 40 50 60 --- 3.0 B -90 30 30 30 30 3.0 (a) The internal rate of return (IRR) for project A is %. (round to two decimals) (b) The internal rate of return (IRR) for project B is %. (round to two decimals) (c) The NPV for project...
Year 0 1 2 3 4 5 6 Project A CF -350 -250 175 225 375...
Year 0 1 2 3 4 5 6 Project A CF -350 -250 175 225 375 450 125 Project B CF -1000 125 250 300 550 500 200 WACC = 12% a. Calculate the NPV of Project A.? b. Calculate the IRR of Project A.? c. Calculate the MIRR of Project A.? d. Calculate the Payback Period for Project B.? e. Calculate the Discounted Payback Period for Project B.? f. Calculate the EAA for Project B.? g. Calculate the crossover...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2 Cash Flow Year 3 Cash Flow Year 4 Cash Flow Discount Rate A -100 40 50 60 N/A .15 B -73 30 30 30 30 .15 Calculate the NPV of both projects. Which project would you accept? If interest rates are now down to 13%, what are the new NPVs?
You are analyzing the following two mutually exclusive projects and have developed the following information. Please...
You are analyzing the following two mutually exclusive projects and have developed the following information. Please calculate the IRRs for the two projects and the crossover rate. Which project should you accept if the cost of capital is 5%, and which project should you accept if the cost of capital is 10%? Year Project A Cash Flow Project B Cash Flow 0 -$84,500 -$76,900 1 $29,000 $25,000 2 $40,000 $35,000 3 $27,000 $26,000 IRR A: ___________ IRR B: ___________ Crossover...
Year 0 CF = -$20,000; Year 1 CF = $3,000; Year 2 CF = $4,000; Year...
Year 0 CF = -$20,000; Year 1 CF = $3,000; Year 2 CF = $4,000; Year 3 CF = $5,000; Year 4 CF = $6,000; Year 5 CF = $7,000. What is the profitability index of the proposed project if the discount rate is 6%? Group of answer choices a. 0.03 b.1.03 c.1.63 d.2.03
1. Consider the following information for projects K and W to answer the following 2 (A...
1. Consider the following information for projects K and W to answer the following 2 (A & B) questions: Project K: NPV = $1,500. IRR = 20% Project W: NPV = $2,500. IRR = 15% A) Assume Project K and Project W are independent projects with a WACC = 10%. Which of the following is true? a. Both Projects K and W should be enacted since both have a positive NPV. b. Neither Project K or W should be enacted...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for 6 years. What is the discounted payback period for this project if the cost of capital is 21%? A) 3.92 years B) 5.61 years C) 4.86 years D) 5.85 years What is the NPV for this project is the cost capital is 21%? A) $157.65 B) -$110.23 C) $199.36 D) $223.08 What is the NPV for this project if the cost of capital is...
Consider the following two mutually exclusive projects: Year 0 Cash Flow(X) - $19,200 Cash Flow(Y) -$19,200...
Consider the following two mutually exclusive projects: Year 0 Cash Flow(X) - $19,200 Cash Flow(Y) -$19,200 Year 1 Cash Flow(X) 8,650 Cash Flow(Y) 9,700 Year 2 Cash Flow(X) 8,700 Cash Flow(Y) 7,600 Year 3 Cash Flow (X) 8,600 Cash Flow (Y) 8,500 A.) Calculate the IRR for each project. Project X ___% Project Y ___% B.) What is the crossover rate for these two projects? C.) What is the NPV of Projects X and Y at discount rates of 0...
Your division is considering two projects with the following cash flows (in millions): 0 1 2...
Your division is considering two projects with the following cash flows (in millions): 0 1 2 3 Project A -$20 $5 $9 $12 Project B -$13 $8 $7 $3 What are the projects' NPVs assuming the WACC is 5%? Enter your answer in millions. For example, an answer of $10,550,000 should be entered as 10.55. Negative values, if any, should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to two decimal places. Project A:    $    million...
You are reviewing a new project and have estimated the following cash flows: Year 0: CF...
You are reviewing a new project and have estimated the following cash flows: Year 0: CF = -170,000; Year 1: CF = 64,120;   Year 2:   CF = 70,800;   Year 3:   CF = 92,330 If the required rate of return is 12%, calculate IRR= (   ). 25 %   6  % 17% 8.7  % 9.5 % 10.5  % 11.8  % 12 % 15.0   % 16    %