Question

Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for...

Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for 6 years. What is the discounted payback period for this project if the cost of capital is 21%?

A) 3.92 years

B) 5.61 years

C) 4.86 years

D) 5.85 years

What is the NPV for this project is the cost capital is 21%?

A) $157.65

B) -$110.23

C) $199.36

D) $223.08

What is the NPV for this project if the cost of capital is 22%?

A) -$134.89

B) - $99.23

C) $111.67

D) -165.41

What is the IRR for this project?

A) 20.12%

B) 21.57

C) 21.88%

D) 22.13%

What is the MIRR for this project is the cost of capital is 21%?

A) 20.76%

B) 21.87%

C) 21.28%

D) 22.19%

Should we accept of reject this project if the cost of capital is 22 percent?

A) Reject since IRR < 0

B) Reject since NPV < 0

C) Accept since IRR > 0

D) Accept since NPV > 0

Homework Answers

Answer #1

Answer to Question 1:

Present Value of Cash Inflow in Year 1 = $5,000/1.21
Present Value of Cash Inflow in Year 1 = $4,132.23

Present Value of Cash Inflow in Year 2 = $5,000/1.21^2
Present Value of Cash Inflow in Year 2 = $3,415.07

Present Value of Cash Inflow in Year 3 = $5,000/1.21^3
Present Value of Cash Inflow in Year 3 = $2,822.37

Present Value of Cash Inflow in Year 4 = $5,000/1.21^4
Present Value of Cash Inflow in Year 4 = $2,332.54

Present Value of Cash Inflow in Year 5 = $5,000/1.21^5
Present Value of Cash Inflow in Year 5 = $1,927.72

Present Value of Cash Inflow in Year 6 = $5,000/1.21^6
Present Value of Cash Inflow in Year 6 = $1,593.15

Company can recover initial investment of $14,629.93 ($4,132.3 + $3,415.07 + $2,822.37 + $2,332.54 + $1,927.72) in first 5 years and remaining $1,370.07 in 6th year

Discount Payback Period = 5 + $1,370.07 / $1,593.15
Discount Payback Period = 5.85 years

Answer to Question 2:

Net Present Value = -$16,000 + $5,000/1.21 + $5,000/1.21^2 + $5,000/1.21^3 + $5,000/1.21^4 + $5,000/1.21^5 + $5,000/1.21^6
Net Present Value = -$16,000 + $5,000 * (1 - (1/1.21)^6) / 0.21
Net Present Value = -$16,000 + $5,000 * 3.244615
Net Present Value = $223.08

Answer to Question 3:

Net Present Value = -$16,000 + $5,000/1.22 + $5,000/1.22^2 + $5,000/1.22^3 + $5,000/1.22^4 + $5,000/1.22^5 + $5,000/1.22^6
Net Present Value = -$16,000 + $5,000 * (1 - (1/1.22)^6) / 0.22
Net Present Value = -$16,000 + $5,000 * 3.166918
Net Present Value = -$165.41

Answer to Question 4:

Let IRR be i%

Net Present Value = -$16,000 + $5,000/(1+i) + $5,000/(1+i)^2 + $5,000/(1+i)^3 + $5,000/(1+i)^4 + $5,000/(1+i)^5 + $5,000/(1+i)^6
0 = -$16,000 + $5,000/(1+i) + $5,000/(1+i)^2 + $5,000/(1+i)^3 + $5,000/(1+i)^4 + $5,000/(1+i)^5 + $5,000/(1+i)^6

Using financial calculator, i = 21.57%

IRR of the project = 21.57%

Answer to Question 5:

Future Value of Cash Inflows = $5,000*1.21^5 + $5,000*1.21^4 + $5,000*1.21^3 + $5,000*1.21^2 + $5,000*1.21 + $5,000
Future Value of Cash Inflows = $5,000 * (1.21^6 - 1) / 0.21
Future Value of Cash Inflows = $5,000 * 10.182992
Future Value of Cash Inflows = $50,914.96

MIRR = (Future Value of Cash Inflows / Present Value of Cash Outflow)^(1/Period) - 1
MIRR = ($50,914.96 / $16,000)^(1/6) - 1
MIRR = 3.182185^(1/6) - 1
MIRR = 1.2128 - 1
MIRR = 0.2128 or 21.28%

Answer to Question 6:

NPV at cost of capital of 22% is negative; therefore, Reject since NPV < 0

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for...
Project S costs $16,000 and is expected to produce cash flows of $5,000 per year for 6 years. What is the discounted payback period for this project if the cost of capital is 21%? A) 3.92 years B) 5.61 years C) 4.86 years D) 5.85 years
Project S costs $16,000 and its expected cash flows would be $4,000 per year for 5...
Project S costs $16,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $29,500 and its expected cash flows would be $9,300 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV < 0. b. Both Projects S and L, since both projects have IRR's > 0. c. Project...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $34,500 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
Consider the following two projects: Project Year 0 CF Year 1 CF Year 2 CF Year...
Consider the following two projects: Project Year 0 CF Year 1 CF Year 2 CF Year 3 CF Year 4 CF Cost of capital A -100 40 50 60 10 15% B -73 30 30 30 30 15% The IRR of project A =? maybe round this one to the closest? A) 7.7% B) 21.6% C) 23.3% D) 42.9% The IRR of project B =? A) 21.6% B) 23.3% C) 42.9% D) 7.7% Which of the following statements is correct?...
Project S costs $19,000 and it's expected cash flows would be $6500 per year for 5...
Project S costs $19,000 and it's expected cash flows would be $6500 per year for 5 years. Mutually exclusive Project L costs $42,500 and it's expected cash flows would be $13,200 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? a. Project L, since NPVL > NPVs b. Both projects S and L, since both projects have IRR's > 0. c. Both projects S and L, since both projects have NPVs...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $8,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0 . c. Both Projects S and...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Project S, since the NPVS > NPVL. c. Neither Project S nor L,...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $37,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0. c. Neither Project S nor L, since each project's NPV...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT
Active Questions
  • Suppose the sale price of a used car can be predicted by a function f(x, y)...
    asked 25 minutes ago
  • Which of the following is the most effective approach to delinquency prevention: psychosocial development or punishment?...
    asked 38 minutes ago
  • You are testing the null hypothesis that there is no linear relationship between two​ variables, X...
    asked 55 minutes ago
  • Using Microsoft Excel functions: 1. A machine will cost $50,000 to purchase. Annual operating cost will...
    asked 57 minutes ago
  • Please, edit for clarity and conciseness, for grammar, capitalization, punctuation, abbreviation, number style, word division, and...
    asked 59 minutes ago
  • Suppose your body was able to use chemical energy in gasoline. How far could you pedal...
    asked 1 hour ago
  • Consider why persons with disabilities are considered a vulnerable population. Share with others experiences you may...
    asked 1 hour ago
  • find the explicit particular solution of the initial value problem 2*x^1/2(dy/dx)=(cos^2)*y y(4)=pi/4 differntial equations
    asked 2 hours ago
  • Soma recorded in the table the height of each player on the basketball team Basketball Players’...
    asked 2 hours ago
  • Program: 6: Function overloading AIM: To write a C++ program to illustrate the concept of function...
    asked 2 hours ago
  • Alumina Ltd. produces a specialty aluminum product, and has the following information available concerning its inventory...
    asked 2 hours ago
  • Write approximately 1,750-2,000 words addressing the following questions: How has globalization impacted health care in the...
    asked 2 hours ago