Question

You are reviewing a new project and have estimated the following cash flows: Year 0: CF...

You are reviewing a new project and have estimated the following cash flows: Year 0: CF = -170,000; Year 1: CF = 64,120;   Year 2:   CF = 70,800;   Year 3:   CF = 92,330

If the required rate of return is 12%, calculate IRR= (   ).

25 %

  6  %

17%

8.7  %

9.5 %

10.5  %

11.8  %

12 %

15.0   %

16    %    

Homework Answers

Answer #1

Computation of IRR:

Year Cash flow Disc @ 12% Discounted Cash flows Disc @ 15% DCF Disc @ 20%
0 -170000 1 -170000 1 -170000 1 -170000
1 64120 0.892857143 57250 0.869565217 55756.52174 0.833333 53433.33
2 70800 0.797193878 56441.32653 0.756143667 53534.97164 0.694444 49166.67
3 92330 0.711780248 65718.67028 0.657516232 60708.47374 0.578704 53431.71
NPV 9409.996811 -0.032875812 -13968.3

We know that at IRR, Present value of the Cash inflows is equal to the cost of the project.So NPV should be 0 at IRR

Hence from the above table we can see that IRR is 15%( Approximately)

So IRR = 15% ( Approximately)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following end of year cash flows (CF) estimate the internal rate of return (IRR)...
Given the following end of year cash flows (CF) estimate the internal rate of return (IRR) of this project. If the project’s cost of capital is 10%, would you undertake this project? Timeline 0 1 2 3 4 CF 0 700 700 700 -3,000 Group of answer choices No; IRR = 18.93% Yes; IRR = 18.93% No; IRR = 7.50% Yes, IRR is greater than the cost of capital
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2 1,281 5 3 1,996 The required return is 8.5%. 1. What is the IRR for the project? 2. What is the NPV of the project? 3 .What should you do? Check all that apply: Reject the project based on its NPV Reject the project based on its IRR Accept the project based on its IRR...
You've estimated the following cash flows (in $) for a project: The required return is 8.5%....
You've estimated the following cash flows (in $) for a project: The required return is 8.5%. What is the IRR for the project? What is the NPV of the project? A B 1 Year Cash flow 2 0 -3,320 3 1 974 4 2 1,281 5 3 1,875
What is the IRR for a project with the following cash flows: Year 0 −5000, Year...
What is the IRR for a project with the following cash flows: Year 0 −5000, Year 1 +3000, Year 2 +4000? A)10.1%B)15.0%C)24.3% D)31.0%
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash...
You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -5,400 3 1 1,325 4 2 2,148 5 3 2,258    Attempt 3/10 for 6 pts. Part 1 What is the IRR for the project?
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year...
Intro You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,200 3 1 974 4 2 1,281 5 3 1,647 The required return is 8.5%. Attempt 1/1 for 10 pts. Part 1 What is the IRR for the project? Submit Attempt 1/1 for 10 pts. Part 2 What is the NPV of the project? Submit Attempt 1/1 for 10 pts. Part 3 What should you do? Check all that apply:...
A project has the following cash flows:    Year Cash Flow 0 $64,700        1 –30,700...
A project has the following cash flows:    Year Cash Flow 0 $64,700        1 –30,700        2 –48,600           Required: (a) What is the IRR for this project? (Click to select)14.26%13.85%13.58%13.04%13.31%     (b) What is the NPV of this project, if the required return is 8.5 percent? (Click to select)$-4,878.46$-5,122.38$4,878.46$-4,683.32$-4,976.03     (c) NPV at 0 percent? (Click to select)$14,600.00$-14,600.00$-14,016.00$-14,892.00$-15,330.00     (d) NPV at 17 percent? (Click to select)$3,016.88$3,105.61$2,957.73$2,839.42$-2,957.73
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...
Projects A and B are mutually exclusive and have the following cash flows: Year Project A...
Projects A and B are mutually exclusive and have the following cash flows: Year Project A Project B 0 -$82,000 -$82,000 1 34,000 0 2 34,000 0 3 34,000 108,000 1. What is the crossover rate? 2. Do we have a conflict in ranking between the NPV and IRR methods if the required rate of return is 8%? 3. Which project should be accepted if the required rate of return is 5%? 4. Which project should be accepted if the...
Given the following cash flows: Year 0 1 2 3 CF -3,500 600 1,000 Cash flow...
Given the following cash flows: Year 0 1 2 3 CF -3,500 600 1,000 Cash flow will grow at a constant rate g=6% We choose the following capital structure plan: Debt Equity Plan 30% 70% Equity Benchmark: The unlevered beta is 2, tax rate is 40%. Market Return is 16%, risk-free rate is 3%. Debt Benchmark: Par:100, Annual Coupon: 6%, 10-year to maturity, Selling at $88.43 What is the NPV of the project? a 1728.42 b 917.53 c 2231.98 d...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT