Question

Consider the following two projects: Project Year 0 Year 1 Year 2 Year 3 Year 4...

Consider the following two projects:

Project Year 0 Year 1 Year 2 Year 3 Year 4 Discount Rate (%)
Cash Flow Cash Flow Cash Flow Cash Flow Cash Flow
A -90 40 50 60 --- 3.0
B -90 30 30 30 30 3.0

(a) The internal rate of return (IRR) for project A is %. (round to two decimals)

(b) The internal rate of return (IRR) for project B is %. (round to two decimals)

(c) The NPV for project A is . (round to two decimals)

(d) The NPV for project B is . (round to two decimals)

Which of the following statements is correct?

A) You should invest in project B since NPV project B > NPV project A and NPV project B > 0.

B) You should invest in project A since IRR project A > IRR project B.

C) Your should invest i project A since NPV project A < 0.

D) You should invest in project A since NPV project A > NPV project B and NPV project A > 0.

The answer is . Fill in "A", "B", "C" or "D".

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the following two projects: Project Year 0 CF Year 1 CF Year 2 CF Year...
Consider the following two projects: Project Year 0 CF Year 1 CF Year 2 CF Year 3 CF Year 4 CF Cost of capital A -100 40 50 60 10 15% B -73 30 30 30 30 15% The IRR of project A =? maybe round this one to the closest? A) 7.7% B) 21.6% C) 23.3% D) 42.9% The IRR of project B =? A) 21.6% B) 23.3% C) 42.9% D) 7.7% Which of the following statements is correct?...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2...
Consider the following two projects: Project Year 0 Cash Flow Year 1 Cash Flow Year 2 Cash Flow Year 3 Cash Flow Year 4 Cash Flow Discount Rate A -100 40 50 60 N/A .15 B -73 30 30 30 30 .15 Calculate the NPV of both projects. Which project would you accept? If interest rates are now down to 13%, what are the new NPVs?
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II)...
Consider the following two mutually exclusive projects: Year Cash Flow (Project I) Cash Flow (Project II) 0 -$12,300 -$44,000 1 $1,800 $14,000 2 $6,000 $30,000 3 $2,000 $5,000 4 $5,000 $10,000 5 $7,000 $5,000 The required return is 10% for both projects. Assume that the internal rate of return (IRR) of Project I and Project II is 18% and 15%, respectively. a) Which project will you choose if you apply the NPV criterion? Why? b) Which project will you choose...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$40,000...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$40,000       –$180,000       1 25,000       15,000       2 22,000       45,000       3 20,000       50,000       4 15,000       275,000       The required return on these investments is 11 percent. Required: (a) What is the payback period for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) Payback period   Project A years     Project B years  ...
You have 3 projects with the following cash​ flows: Year: 0 1 2 3 4 Project...
You have 3 projects with the following cash​ flows: Year: 0 1 2 3 4 Project 1: -$ 148 $ 20 $ 42 $ 60 $ 81 Project 2: -826 0 0 6,994 -6,510 Project 3: 21 40 58 78   -44 a. For which of these projects is the IRR rule​ reliable? b. Estimate the IRR for each project​ (to the nearest 1 %​). c. What is the NPV of each project if the cost of capital is 5 %​?...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$ 424,000 –$ 39,500 1 44,500 20,300 2 61,500 13,400 3 78,500 18,100 4 539,000 14,900    The required return on these investments is 11 percent. a. What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback period Project A years Project B years b. What is the NPV for each...
Mahjong, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash...
Mahjong, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$37,300        –$37,300        1 19,660        7,180        2 15,170        13,680        3 12,660        20,160        4 9,660        24,160          Required: (a) What is the IRR for Project A? (b) What is the IRR for Project B? (c) If the required return is 11 percent, what is the NPV for Project A? (d) If the required...
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash...
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$37,000        –$37,000        1 19,000        6,000        2 14,500        12,500        3 12,000        19,000        4 9,000        23,000          a. What is the IRR for Project A?    b. What is the IRR for Project B?    c. If the required return is 11 percent, what is the NPV for Project A?    d. If...
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash...
Bruin, Inc., has identified the following two mutually exclusive projects:    Year Cash Flow (A) Cash Flow (B) 0 –$37,000        –$37,000        1 19,000        6,000        2 14,500        12,500        3 12,000        19,000        4 9,000        23,000          a. What is the IRR for Project A?    b. What is the IRR for Project B?    c. If the required return is 11 percent, what is the NPV for Project A?    d. If...