Question

1. Consider the following information for projects K and W to answer the following 2 (A...

1. Consider the following information for projects K and W to answer the following 2 (A & B) questions:

Project K: NPV = $1,500. IRR = 20%

Project W: NPV = $2,500. IRR = 15%

A) Assume Project K and Project W are independent projects with a WACC = 10%. Which of the following is true?

a. Both Projects K and W should be enacted since both have a positive NPV.

b. Neither Project K or W should be enacted since both have a positive NPV.

c. Only Project W should be enacted since it has the highest NPV.

d. Only Project K should be enacted since it has the highest IRR.

B. Assume Project K and Project W are mutually exclusive projects with a WACC = 10%. Which of the following is true?

a. Only Project W should be enacted since it has the highest NPV.

b. Neither Project K or W should be enacted since both have a positive NPV.

c. Both Projects K and W should be enacted since both have a positive NPV.

d. Only Project K should be enacted since it has the highest IRR.  

Homework Answers

Answer #1

Part A: Option a is correct. Both Projects should be enacted.
In case of independent projects, the cash flows of one project is not affected whether we accept or reject the other project. So, when NPV>0 and the projects are independent, we can accept both the projects.

Part B:Option a is correct.
Only Project W should be enacted as it has highest NPV.
In case of mutually exclusive projects only one project should be accepted. Between the two projects, we should accept the project with highest NPV because it increases the value of a business.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company has the option to invest in project A, project B, or neither (the projects...
A company has the option to invest in project A, project B, or neither (the projects are mutually exclusive and the company has no other investment options). Project A requires an initial investment of $100,000 today and provides cash flows of $35,000 a year for five years. The project will also return back $20,000 in capital in year six. Project B requires a $135,000 investment today and will have cash flows of $40,000 a year for 5 years. The firm’s...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of return of 8.25%. You have gathered the following data. Which of the project(s) should be accepted? IRR NPV Project A 6.40% $ 22.6 million Project B 8.50% $ 16.1 million A) Accept neither project, as both have a required return that is above the IRR. B) Accept project B with the higher IRR. C) Accept project A with the higher NPV. D) Accept both...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have the same initial outlay. Project Adam has an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, the projects have different lives, and the projects are not repeatable. What should you do? You should do Project...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$500 $45 $45 $45 $220 $220 Project B -$600 $300 $300 $50 $50 $50 Which project would you recommend? Select the correct answer. I. Neither A or B, since each project's NPV < 0. II. Both Projects A and B, since both projects have NPV's > 0. III. Both Projects A and...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $70 $70 $70 $235 $235 Project 2 -$400 $250 $250 $140 $140 $140 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Project 1, since the NPV1 > NPV2. d. Both Projects 1 and 2, since...