Question

Two firms examined the same capital budgeting project which had an IRR of 16%. One firm...

Two firms examined the same capital budgeting project which had an IRR of 16%. One firm accepted the project but the other rejected it. One of the firms must have made an incorrect decision.

Discuss the validity of this statement. Be specific.

Can I have original answer. Thank you

Homework Answers

Answer #1

Discuss the validity of this statement. ?

The statement is incorrect. Internal rate of return (IRR) is the return that make Present Value of Cashoutflow is equal to present value of cashinflow.

Different companies have different cost of capital and the firm which accept the project have lower cost of capital than 16% and the firm which reject the project have higher cost of capital than 16%.

Hence the statement is not correct.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company takes on a project that has an IRR of 10% which is the same...
A company takes on a project that has an IRR of 10% which is the same as its cost of capital. Is this a good decision? Select one: a. No. Only projects with positive NPV’s should be accepted. b. Perhaps, depending on the situation. This project has an NPV of zero and though not increasing the wealth of the company it may place the company in a better strategic position in the business environment. c. Depends on the payback period...
Capital Budgeting: 1. T/F If the NPV<0, the WACC > the IRR 2.T/F Salvage value is...
Capital Budgeting: 1. T/F If the NPV<0, the WACC > the IRR 2.T/F Salvage value is added back in to the last years projects cash flows 3. T/F NPV is considered to be the superior method for choosing capital budget projects 4. T/F If projects are mutually exclusive, if one has a higher IRR choose that project over the NPV decision. Cost of Capital 5. T/F external equity (new stock issuance) is less expensive since it will have a flotation...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
Which of the following is FALSE? Select one: a. Capital budgeting is the process of evaluating...
Which of the following is FALSE? Select one: a. Capital budgeting is the process of evaluating and selecting short-term investments that are consistent with the firm's goal of maximizing owners' wealth. b. The purchase of additional physical facilities, such as additional property or a new factory, is an example of a capital expenditure. c. Capital budgeting techniques are used to evaluate a firm's fixed asset investments which provide the basis for the firm's earning power and value. d. Capital expenditure...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
Mento Mills is considering two mutually exclusive projects. The Amber Project has an internal rate of...
Mento Mills is considering two mutually exclusive projects. The Amber Project has an internal rate of return (IRR) of 12 percent, while Bukka Project has an IRR of 14 percent. The two projects have very similar risk. Both projects have the same NPV when the cost of capital is 7 percent. Assume each project has an initial cash investment followed by a series of cash returns. The following are possible statements that can be made about this information: I. If...
Mento Mills is considering two mutually exclusive projects. The Amber Project has an internal rate of...
Mento Mills is considering two mutually exclusive projects. The Amber Project has an internal rate of return (IRR) of 12 percent, while Bukka Project has an IRR of 14 percent. The two projects have very similar risk. Both projects have the same NPV when the cost of capital is 7 percent. Assume each project has an initial cash investment followed by a series of cash returns. The following are possible statements that can be made about this information: I. If...
Suppose your firm would like to earn 10% yearly return from the following two investment projects...
Suppose your firm would like to earn 10% yearly return from the following two investment projects of equal risk. Year (t) Cash flows from Project A (Ct) Cash flows from Project B (Ct) 0 –$8,000 –$8,000 1 $2,000 $4,000 2 $3,000 $2,000 3 $5,000 $2,500 4 $1,000 $2,000 (a) If only one project can be accepted, based on the NPV method which one should it be? Support your answer with calculations. (b) Suppose there is another four-year project (Project C)...