Question

CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...

CAPITAL BUDGETING CRITERIA

A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:

0 1 2 3 4 5
Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000
Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800
  1. Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations.
    Project M    $
    Project N    $

    Calculate IRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
    Project M      %
    Project N      %

    Calculate MIRR for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
    Project M      %
    Project N      %

    Calculate payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
    Project M      years
    Project N      years

    Calculate discounted payback for each project. Round your answers to two decimal places. Do not round your intermediate calculations.
    Project M      years
    Project N      years

  2. Assuming the projects are independent, which one(s) would you recommend?
    -Select-Both projects would be accepted since both of their NPV's are positive.Only Project M would be accepted because IRR(M) > IRR(N).Both projects would be rejected since both of their NPV's are negative.Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Item 11
  3. If the projects are mutually exclusive, which would you recommend?
    -Select-If the projects are mutually exclusive, the project with the shortest Payback Period is chosen. Accept Project M.If the projects are mutually exclusive, the project with the highest positive IRR is chosen. Accept Project N.If the projects are mutually exclusive, the project with the highest positive NPV is chosen. Accept Project N.If the projects are mutually exclusive, the project with the highest positive IRR is chosen. Accept Project M.If the projects are mutually exclusive, the project with the highest positive MIRR is chosen. Accept Project M.Item 12
  4. Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRR?
    -Select-The conflict between NPV and IRR occurs due to the difference in the size of the projects.The conflict between NPV and IRR is due to the relatively high discount rate.The conflict between NPV and IRR is due to the fact that the cash flows are in the form of an annuity.The conflict between NPV and IRR is due to the difference in the timing of the cash flows.There is no conflict between NPV and IRR.Item 13

Homework Answers

Answer #1

1.
=NPV(14%,{-18000;6000;6000;6000;6000;6000})*(1+14%)=2598.48581315076

2.
=NPV(14%,{-54000;16800;16800;16800;16800;16800})*(1+14%)=3675.76027682212

3.
=IRR({-18000;6000;6000;6000;6000;6000})=19.8577097873066%

4.
=IRR({-54000;16800;16800;16800;16800;16800})=16.7976214212598%

5.
=MIRR({-18000;6000;6000;6000;6000;6000},14%,14%)=17.1163178493378%

6.
=MIRR({-54000;16800;16800;16800;16800;16800},14%,14%)=15.5113780416976%

7.
=18000/6000=3.00

8.
=54000/16800=3.21428571428571

9.
=NPER(14%,-6000,18000)=4.15732579702627

10.
=NPER(14%,-16800,54000)=4.56265686330585

11.
Both projects would be accepted since both of their NPV's are positive

12.
If the projects are mutually exclusive, the project with the highest positive NPV is chosen. Accept Project N.

13.
The conflict between NPV and IRR occurs due to the difference in the size of the projects

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$500 $45 $45 $45 $220 $220 Project B -$600 $300 $300 $50 $50 $50 Which project would you recommend? Select the correct answer. I. Neither A or B, since each project's NPV < 0. II. Both Projects A and B, since both projects have NPV's > 0. III. Both Projects A and...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$400 $65 $65 $65 $210 $210 Project 2 -$400 $300 $300 $55 $55 $55 Which project would you recommend? Select the correct answer. I. Both Projects 1 and 2, since both projects have NPV's > 0. II. Project 2, since the NPV2 > NPV1. III. Neither A or B, since each project's...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $45 $45 $45 $160 $160 Project 2 -$450 $300 $300 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $40 $40 $40 $215 $215 Project 2 -$650 $200 $200 $70 $70 $70 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Project 2, since the NPV2 > NPV1....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $75 $75 $75 $170 $170 Project 2 -$700 $200 $200 $50 $50 $50 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Project 1, since...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $50 $50 $50 $175 $175 Project 2 -$700 $350 $350 $80 $80 $80 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both projects have NPV's > 0....
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%. 0 1 2 3 4 Project A...