Question

A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...

A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows:

0 1 2 3 4 5
Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000
Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400
  1. Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent.

    Project M:    $  

    Project N:    $  

    Calculate IRR for each project. Do not round intermediate calculations. Round your answers to two decimal places.

    Project M:       %

    Project N:       %

    Calculate MIRR for each project. Do not round intermediate calculations. Round your answers to two decimal places.

    Project M:       %

    Project N:       %

    Calculate payback for each project. Do not round intermediate calculations. Round your answers to two decimal places.

    Project M:      years

    Project N:      years

    Calculate discounted payback for each project. Do not round intermediate calculations. Round your answers to two decimal places.

    Project M:      years

    Project N:      years

  2. Assuming the projects are independent, which one(s) would you recommend?

    -Select-Only Project M would be accepted because NPV(M) > NPV(N).Only Project N would be accepted because NPV(N) > NPV(M).Both projects would be accepted since both of their NPV's are positive.Only Project M would be accepted because IRR(M) > IRR(N).Both projects would be rejected since both of their NPV's are negative.Item 11

  3. If the projects are mutually exclusive, which would you recommend?

    -Select-If the projects are mutually exclusive, the project with the highest positive NPV is chosen. Accept Project N.If the projects are mutually exclusive, the project with the highest positive IRR is chosen. Accept Project M.If the projects are mutually exclusive, the project with the highest positive MIRR is chosen. Accept Project M.If the projects are mutually exclusive, the project with the shortest Payback Period is chosen. Accept Project M.If the projects are mutually exclusive, the project with the highest positive IRR is chosen. Accept Project N.Item 12

  4. Notice that the projects have the same cash flow timing pattern. Why is there a conflict between NPV and IRR?

    -Select-The conflict between NPV and IRR is due to the fact that the cash flows are in the form of an annuity.The conflict between NPV and IRR is due to the difference in the timing of the cash flows.There is no conflict between NPV and IRR.The conflict between NPV and IRR occurs due to the difference in the size of the projects.The conflict between NPV and IRR is due to the relatively high discount rate.

Homework Answers

Answer #1

1.
=PV(14%,5,-3000)-9000=1299.24290657539

2.
=PV(14%,5,-8400)-27000=1837.88013841108

3.
=RATE(5,-3000,9000)=19.8577097872901%

4.
=RATE(5,-8400,27000)=16.7976214212599%

5.
=MIRR({-9000;3000;3000;3000;3000;3000},14%,14%)=17.1163178493378%

6.
=MIRR({-27000;8400;8400;8400;8400;8400},14%,14%)=15.5113780416976%

7.
=9000/3000=3.00

8.
=27000/8400=3.21428571428571

9.
=NPER(14%,-3000,9000)=4.15732579702627

10.
=NPER(14%,5,-8400,27000)=8.93351004270202

11.
Both projects would be accepted since both of their NPV's are positive

12.
If the projects are mutually exclusive, the project with the highest positive NPV is chosen. Accept Project N

13.
The conflict between NPV and IRR occurs due to the difference in the size of the projects

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M: $ Project N: $ Calculate IRR for each project. Do not round intermediate calculations. Round your...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%. 0 1 2 3 4 Project A...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%. 0 1 2 3 4 Project A...
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent....
Crane Corp. management is evaluating two mutually exclusive projects. The cost of capital is 15 percent. Costs and cash flows for each project are given in the following table. Year Project 1 Project 2 0 -$1,292,224 -$1,321,796 1 238,000 384,000 2 329,000 384,000 3 430,000 384,000 4 504,000 384,000 5 800,000 384,000 Calculate NPV and IRR of two projects. (Enter negative amounts using negative sign, e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to...
Question 1. Bigg company is evaluating two projects for next year’s capital budget. The after-tax cash...
Question 1. Bigg company is evaluating two projects for next year’s capital budget. The after-tax cash flows (including depreciation) for each project are the following: Project A Project B Year 0 -6,000 -18,000 Year 1 2,000 5,600 Year 2 2,000 5,600 Year 3 2,000 5,600 Year 4 2,000 5,600 Year 5 2,000 5,600 Year 6 4,000 9,000 a.) If the company’s WACC is 14%, find the NPV, IRR, payback, and discount payback for each project. b.) If the projects are...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of return of 8.25%. You have gathered the following data. Which of the project(s) should be accepted? IRR NPV Project A 6.40% $ 22.6 million Project B 8.50% $ 16.1 million A) Accept neither project, as both have a required return that is above the IRR. B) Accept project B with the higher IRR. C) Accept project A with the higher NPV. D) Accept both...
A firm is evaluating two projects for this year’s capital budget. Its WACC is 14%. Project...
A firm is evaluating two projects for this year’s capital budget. Its WACC is 14%. Project A costs $5,500 and its expected cash inflows would be $2,000 per year for 5 years. Project B costs $18,800 and its expected cash inflows would be $5,600 per year for 5 years. If the projects were mutually exclusive, which one would you recommend? If the projects were independent, which one(s) would you recommend? Explain.
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,400 –$ 8,800 1 8,000 3,500 2 6,600 3,000 3 2,100 5,400 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project A Project B If the appropriate discount rate is 13...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT