Part a) NPV of A is calculated below:
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -8,000.00 | 1/(1+0.1)^0= | 1 | 1*-8000= | $ -8,000.00 |
1 | $ 2,000.00 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*2000= | $ 1,818.18 |
2 | $ 3,000.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*3000= | $ 2,479.34 |
3 | $ 5,000.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*5000= | $ 3,756.57 |
4 | $ 1,000.00 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*1000= | $ 683.01 |
NPV = Sum of all Discounted CF | $ 737.11 |
NOV of B is below:
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -8,000.00 | 1/(1+0.1)^0= | 1 | 1*-8000= | $ -8,000.00 |
1 | $ 4,000.00 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*4000= | $ 3,636.36 |
2 | $ 2,000.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*2000= | $ 1,652.89 |
3 | $ 2,500.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*2500= | $ 1,878.29 |
4 | $ 2,000.00 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*2000= | $ 1,366.03 |
NPV = Sum of all Discounted CF | $ 533.57 |
NPV of A is higher so it should be selected
Part b)
i) Basically Projects B and C have the same CFs only the timing is reversed, therefore both will have an equal NPV if the discount rate =0, for any other discount rate, the projects will have different NPVs because, if we calculate the payback period of both, we will get to know that under project B the initial investment is recovered sooner as it has higher CFs at the beginning.
ii) As explained above, even if the risk is same, the recovery is sooner in Project B so it is better to pick that.
iii) Using goal-seek, we need to determine the 4th CF which makes the NPV = 0 at 10% discount rate, so any CF greater than that, the project is worth accepting. The same has been done below:
Year | CF | Discount Factor | Discounted CF | ||
0 | $ -8,000.00 | 1/(1+0.1)^0= | 1 | 1*-8000= | $ -8,000.00 |
1 | $ 2,000.00 | 1/(1+0.1)^1= | 0.909090909 | 0.909090909090909*2000= | $ 1,818.18 |
2 | $ 2,500.00 | 1/(1+0.1)^2= | 0.826446281 | 0.826446280991735*2500= | $ 2,066.12 |
3 | $ 2,000.00 | 1/(1+0.1)^3= | 0.751314801 | 0.751314800901578*2000= | $ 1,502.63 |
4 | $ 3,825.80 | 1/(1+0.1)^4= | 0.683013455 | 0.683013455365071*3825.8= | $ 2,613.07 |
NPV = Sum of all Discounted CF | $ 0.00 |
Therefore the CF4 should be greater than $3,825.80 for it to be acceptable
iv) Payback period is calculated below:
Project B:
Year | Opening Balance | Investment | CF | Closing Balance |
0 | $ 8,000.00 | $ 8,000.00 | ||
1 | $ 8,000.00 | $ 4,000.00 | $ 4,000.00 | |
2 | $ 4,000.00 | $ 2,000.00 | $ 2,000.00 | |
3 | $ 2,000.00 | $ 2,500.00 | $ -500.00 | |
4 | $ -500.00 | $ 2,000.00 | $ -2,500.00 |
We see that the closing balance at the end of year 2 was 2000 and the CF for year 3 was 2500 so in 2000/2500 = 2.8 years the initial investment is recovered. If the cutoff is set at 3 years then project B is acceptable
Project C:
Year | Opening Balance | Investment | CF | Closing Balance |
0 | $ 8,000.00 | $ 8,000.00 | ||
1 | $ 8,000.00 | $ 2,000.00 | $ 6,000.00 | |
2 | $ 6,000.00 | $ 2,500.00 | $ 3,500.00 | |
3 | $ 3,500.00 | $ 2,000.00 | $ 1,500.00 | |
4 | $ 1,500.00 | $ 4,000.00 | $ -2,500.00 |
We see that the closing balance at the end of year 3 was 1500 So the initial investment will be recovered in coming years if it is recovered at all so Project C doesn't meet the criteria of 3 years.
Part c) If we don't use any discounting, the sum of inflows > the outflow, therefore the IRR should be positive because it is the discount rate used to have a 0 NPV, that is the sum of all CFs, positive and negative can only be 0 if the discount rate > 0% and therefore the IRR will have to be > % or positive.
Part d) 10% is the required rate, or the discount rate for projects, which means that the project will have to have a minimum return of 10% because of the risks associated with it for the project to be worth it. Therefore, we use this return to discount the CFs and see if NPV is positive, if that is the case then our actual return is greater than 10% so we have met the criteria and have earned greater return than the risk. Or we can even say that the IRR is greater because that is the return which is used to reinvest the CFs
Get Answers For Free
Most questions answered within 1 hours.