Question

A company takes on a project that has an IRR of 10% which is the same...

A company takes on a project that has an IRR of 10% which is the same as its cost of capital. Is this a good decision?

Select one:

a. No. Only projects with positive NPV’s should be accepted.

b. Perhaps, depending on the situation. This project has an NPV of zero and though not increasing the wealth of the company it may place the company in a better strategic position in the business environment.

c. Depends on the payback period of the project.

d. No. In such cases, the company should seek a vote from its shareholders before a decision to go ahead should be taken.

Homework Answers

Answer #1

The answer is Option B (Perhaps, depending upon the situation. The project has an NPV of zero and though not increasing the wealth of the company, it mapy place the company in a better strategic position in the business environment.)
This means that even though the project is not making any value additions, it can offer other strategic edges which is beneficial in the long run of the company.

Option A is wrong since positive NPV is not the only criteria for making a project decision. NPV may be of +$1, but that doesn't mean we should accept the project.

Option C is wrong since the payback period is also of one of the criteria & payback period is not mentioned in the problem too.

Option D is wrong since these decisions are considered by the top management of the company.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
Which of the following is statements related to capital budgeting is not true? A project is...
Which of the following is statements related to capital budgeting is not true? A project is considered acceptable if its NPV is greater zero. A project whose NPV is greater than its IRR is should be accepted. Both the NPV method and the IRR method of evaluating capital investment projects are widely considered to be superior to the payback method. An NPV of zero signifies that the project's cash flows are just sufficient to repay the invested capital and to...
11-1 If Company XYZ plans to invest in a project with initial capital outlay $52,125, annual...
11-1 If Company XYZ plans to invest in a project with initial capital outlay $52,125, annual net cash inflow $12,000 for 8 years, and discount rate 12%, what is the Company XYZ’s NPA? 11-2 For the Company XYZ’s same project as in 11-1, what is the IRR for the project? There are two projects: Project A and Project B Project A: CF0 = -6000; CF1-5 = 2000; I/YR = 14. Calculate NPV, IRR, MIRR, Payback period, and discounted payback period...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: The...
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost...
Puckett Inc. risk-adjusts its WACC to account for project risk. It uses a risk-adjusted project cost of capital of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the following independent projects should Puckett accept, assuming that the company uses the NPV method when choosing projects? a. Project C, which has above-average risk and an IRR = 11%. b. Without information about the projects' NPVs we cannot determine which project(s) should be...
You are a financial analyst for Hittle Company. The director of capital budgeting has asked you...
You are a financial analyst for Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each project is 10 percent. The payback cutoff period is 3 years. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project X 0 ($10,000) 1 6,500 2 3,000 3 3,000 4 1,000 Project Y ($10,000)...
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash...
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. Is this a good project if the required return is 8 percent? What if it's 24 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?  LO 4 9. Calculating NPV. For the cash flows in the previous problem, what is the NPV at a discount rate of...
Suppose your firm is considering investing in a project with the cash flows shown below, that...
Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 11 percent, and that the maximum allowable payback and discounted payback statistics for your company are 3 and 3.5 years, respectively. Time: 0 1 2 3 4 5 Cash flow –$235,000 $65,800 $84,000 $141,000 $122,000 $81,200 Use the IRR decision rule to evaluate this project. (Do not round intermediate calculations and round...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
Senior management asks you to recommend a decision on which project(s) to accept based on the...
Senior management asks you to recommend a decision on which project(s) to accept based on the cash flow forecasts provided. Relevant information: The firm uses a 3-year cutoff when using the payback method. The hurdle rate used to evaluate capital budgeting projects is 15%. The cash flows for projects A, B and C are provided below. Project A Project B Project C Year 0 -30,000 -20,000 -50,000 Year 1 0 4,000 20,000 Year 2 7,000 5,000 20,000 Year 3 20,000...