Server Farm Inc. (SFI) needs to upgrade its server
computers. Company management has identifi ed the
following two options: (1) shift to a Windows - based
platform from its current Unix - based platform, or (2)
stick with a Unix - based platform. It is standard practice
at SFI to use a triangular distribution to model
uncertain costs.
Along these lines, the company estimates that
if it migrates to Windows, the new server hardware
could cost as little as $100,000 or as much as
$200,000. The technical group ’ s best estimate is that
the hardware costs will be $125,000 if the Window ’ s
option is pursued. Likewise, the company ’ s best
guess regarding the cost to upgrade and convert its
software to Windows is $300,000 with a range of
$275,000 to $500,000. Finally, if the company converts
to Windows, employee training costs are estimated
to range between $9,000 and $15,000, with
the best guess being $10,000. If the company sticks
with Unix, the new server hardware will most likely
cost $100,000, but could cost as little as $80,000
or as much as $210,000. Software conversion and
upgrade costs are expected to be $300,000 but could
be as low as $250,000 and as high as $525,000.
Employee training costs should fall between $8,000
and $17,500, with a best guess of $10,000. Develop
a model to simulate this situation using CB and
answer the following questions.
(a) What is the expected cost of each project?
(b) What is the probability that each project ’ s cost
will exceed $575,000?
(c) Which project would you consider to be the
most risky?
(d) Which project would you recommend SFI
undertake? Why?
c. More the standard deviation more it is risky. So UNIX is more risky.
d. Because the windows project is less risky so it will be taken.