Question

Would a contractor prefer a cost reimburseable contract or a fixed price contract? Why?

Would a contractor prefer a cost reimburseable contract or a fixed price contract? Why?

Homework Answers

Answer #1

First of all...cost reimbursement contract is a contract where a contractor is paid for all of its allowed expenses to a set of limit, plus additional payment to allow for a profit. And fixed price contract provides for a price that is not subject to adjustment on the basis of the contractor's cost experience in the performing the contract.

So contractor would prefer reimbursement contract over fixed price contract. The contractor will receive reimbursement for all cost and still make profit but under fixed price contract, there is a risk that the cost will be greater than the price and thus the contractor will take loss.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
  On which side of the (compaction) curve would a contractor prefer to be, and why?
  On which side of the (compaction) curve would a contractor prefer to be, and why?
Explain why a company would prefer a foreign currency option over a forward contract in hedging...
Explain why a company would prefer a foreign currency option over a forward contract in hedging a foreign currency firm commitment, and why a company would prefer a forward contract over an option in hedging a foreign currency asset or liability.
The owner and the contractor on a school project entered into a unit-price contract. During the...
The owner and the contractor on a school project entered into a unit-price contract. During the construction phase, the owner required the contractor to do certain minor work and materials items to be furnished for which there is no stated payment item in the contract, what shall the contractor probably do to obtain compensation for the work and required materials? Explain.
Mike hires a contractor to build him a house. Mike agrees to pay the contractor $1...
Mike hires a contractor to build him a house. Mike agrees to pay the contractor $1 million and the contractor agrees to build the 2,000 square feet house according to Mike’s specifications. In EACH case below, is there a valid consideration? Why? Why Not? Anwer and explain in terms of five consideration rules or/and exceptions to the preexisting rule. Case 1: During the construction, the contractor informs Mike that he will not build the house for less than $1.5 million....
A contractor at the end of its s second year working on a contract finds that...
A contractor at the end of its s second year working on a contract finds that the total estimated cost of the contract ($600,000) exceeds the contract price ($550,000). At the end of the first year of the contract, $20,000 of gross profit was recognized. The percentage of completion at the end of year 2 is 40%. What amount of loss is recognized for the second year? 20,000 50,000 70,000 40,000 10,000
JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,320,000....
JRE2 Inc. entered into a contract to install a pipeline for a fixed price of $2,320,000. JRE2 recognizes revenue upon contract completion. Cost incurred Estimated Cost to Complete 2020 $ 266,000 $ 1,630,000 2021 1,680,000 588,000 2022 530,000 0 In 2022, JRE2 would report gross profit (loss) of: Multiple Choice $(156,000). $102,000. $58,000. $19,333.
Apple and Compaq both seek funding at the lowest possible cost. Apple would prefer the flexibility...
Apple and Compaq both seek funding at the lowest possible cost. Apple would prefer the flexibility of floating rate borrowing, while Compaq wants the security of fixed rate borrowing. They face the following interest rate structure: (1) Apple could borrow floating at LIBOR + 1% or borrow fixed at 8%; (2) Apple prefers floating rate debt; (3) Compaq could borrow floating at LIBOR + 2% or borrow fixed at 12%; and (4) Compaq prefers a fixed rate. a. To arrange...
The City of Atlanta awarded a contract to a general contractor to construct an irrigation dam....
The City of Atlanta awarded a contract to a general contractor to construct an irrigation dam. The contract stipulates some amount for liquidated damages for delay. After the construction has started, the City had to make some corrections to the plan which consequently affected the contractor's schedule. The contractor did not ask for extension of time or propose a change order to the contract. The contractor completed the work 15 days behind the schedule. The City sued for liquidated damages...
The probability that a contractor will win a bid for contract A is 0.45; the probability...
The probability that a contractor will win a bid for contract A is 0.45; the probability that the contractor will win a bid for contract B is 0.25. The two bids are believed to be independent of each other. What is the probability that the contractor will win at least one of the two bids? Group of answer choices 0.70 0.20 0.1125 0.5875 0.5556 The probability that I get job A is 0.45; the probability that I get job B...
Contract allowed Contractor 290 days to complete construction of fire station. Some of the drawings furnished...
Contract allowed Contractor 290 days to complete construction of fire station. Some of the drawings furnished by Owner proved defective. This delayed Contractor's performance of the work. Owner became dissatisfied with the pace of Contractor's progress and terminated the contract for default. Contractor contested the termination. Discussion Do you agree with the Owner's decision to terminate the contract? Based on your knowledge of construction contract risk management, how do you think the court would rule on this case? In whose...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT