Question

A contractor at the end of its s second year working on a contract finds that...

A contractor at the end of its s second year working on a contract finds that the total estimated cost of the contract ($600,000) exceeds the contract price ($550,000). At the end of the first year of the contract, $20,000 of gross profit was recognized. The percentage of completion at the end of year 2 is 40%. What amount of loss is recognized for the second year?

20,000

50,000

70,000

40,000

10,000

Homework Answers

Answer #1

Given that

Total contact price $550000

Percentage completed as on last day of 2nd year is 40%

Profit recognised in 1st year $20000 has no relevance for 2nd year.

As per IFRS, in case, if contractors estimated contract cost exceeds the contract price, then recognise the whole probable loss in year of estimated.

Means, in the given sum, contractors estimated cost of contract $600000 exceeds the contract price of $550000 at the end of 2nd year.So as per IFRS, he needs to recognise whole loss I.e., $600000-$550000=$50000 in the 2nd year itself irrespective of percentage of completion.

Amount of loss recognized in 2nd year is $50000.

Thank you.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows: First year Second year Third year Costs during year 40,000 80,000 50,000 Estimated costs to complete 120,000 80,000 -- How much gross profit should be recognized a the end of each year, assuming Jackson recognizes revenue over time according to percentage of completion?
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed...
On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed by the end of 2021. The cataract price is $2,500,000. ACDC Co provides the following information for the project progress. Details 2019 2020 2021 Cost incurred to date $600,000 $1,400,000 $2,100,000 Estimated cost to complete $900,000 $600,000 $0 Customer billings $500,000 $600,000 $350,000 Cash collections $400,000 $500,000 $300,000 Assuming that ACDC uses the percentage of completion method, the cost incurred (used) in 2020 is...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that...
On January 1, Year 1, a contractor began work on a $3.2 million construction contract that is expected to be completed in 3 years. The contractor concludes that it is appropriate to recognize revenue over time using the input method based on costs incurred (cost-to-cost method). At the inception date, the estimated cost of construction was $2.4 million. The following data relate to the actual and expected construction costs: Year 1 Year 2 Year 3 Cost incurred $720,000 $1,170,000 $1,110,000...
The following information relates to a contract through its second year. The contract price is $100,000....
The following information relates to a contract through its second year. The contract price is $100,000. 558 Year 1 Year 2 Cost incurred through end of $40,000 $80,000 Estimated cost remaining at end of 45,000 34,000 Under the completed contract method, by what amount will pretax income for the second year be affected? A. Reduced $14,000 B. Reduced $34,000 C. Reduced $15,000 D. No effect Cans Corp. had outstanding 3,000 shares of 10% preferred stock, $100 par. On August 8,...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...