Question

The owner and the contractor on a school project entered into a unit-price contract. During the...

The owner and the contractor on a school project entered into a unit-price contract. During the construction phase, the owner required the contractor to do certain minor work and materials items to be furnished for which there is no stated payment item in the contract, what shall the contractor probably do to obtain compensation for the work and required materials? Explain.

Homework Answers

Answer #1

If there are additional works to be done by contractor, for which there is no specific item mentioned in the original contract, the contractor has two options to recover his costs for the aforesaid extra work:

1. The contractor can submit the quotation of unit rate for the extra item/s to the owner and have them approved and added to the original contract. The approval might depend on the quoted cost and if there will be any delay in the project since new items added will alter the project schedule / plan.

2. If the above option is not viable, the contractor has option to adjust the rates of his original items mensioned in original contract, so that he incorporate the cost of additional items in the unit rate of original items, so that he does not suffer a loss due to extra work done by him. The revision in rates will have to be approved by the owner as well.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A 201 General conditions contractor for construction contract 1what the cost to owner to determine a...
A 201 General conditions contractor for construction contract 1what the cost to owner to determine a project for "convenience"? The contractor on countered materially different site conditions during excavation. In order to make a claim for additional cost, when does he have to file the claim? Does the owner have right to reject contractor's (GC'S) subcontractor who is reasonably capable of performing the work?
THIS TEACHING CONTRACT (''Contract'') is entered into and becomes effective as of August 11, 2019 by...
THIS TEACHING CONTRACT (''Contract'') is entered into and becomes effective as of August 11, 2019 by and between Pretend Community College (''Employer''), and Mandy Gruhlkey (''Employee''). IN CONSIDERATION of the promises and of the mutual covenants contained herein, and for other good and valuable consideration, receipt of which is hereby acknowledged, the parties hereto do hereby agree as follows: 1. Employment. Employer hereby engages Employee to serve as a political science and business professor and Employee hereby accepts such an...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
Martinez Construction Company began work on a $419,500 construction contract in 2020. During 2020, Martinez incurred...
Martinez Construction Company began work on a $419,500 construction contract in 2020. During 2020, Martinez incurred costs of $282,500, billed its customer for $232,500, and collected $181,000. At December 31, 2020, the estimated additional costs to complete the project total $164,140. Prepare Martinez’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Larkspur Construction Company began work on a $403,500 construction contract in 2020. During 2020, Larkspur incurred...
Larkspur Construction Company began work on a $403,500 construction contract in 2020. During 2020, Larkspur incurred costs of $263,000, billed its customer for $209,500, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $160,510. Prepare Larkspur’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Bryan followed in his father’s footsteps and entered into the carpet business. He owns and operates...
Bryan followed in his father’s footsteps and entered into the carpet business. He owns and operates I Do Carpet (IDC). Bryan prefers to install carpet only, but in order to earn additional revenue, he also cleans carpets and sells carpet-cleaning supplies. A. IDC contracted with a homebuilder in December of last year to install carpet in 10 new homes being built. The contract price of $87,500 includes $53,000 for materials (carpet). The remaining $34,500 is for IDC’s service of installing...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Correct answer iconYour answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to...
Case Abstract: Company ABC, an AE, constructor and construction management firm, recently assigned Bob Ironside to turn a major coal fired generating station project around. Currently at 36 percent construction completion, the project is shifting from an emphasis on civil and structural work to bulk production. Cooperation of the owner, the multi-prime contractors, and strong labor unions is cach vital for performance improvement. The analysis of this project involves: 1) identification of significant external influences on the project organization, 2)...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
Flounder, Inc. began work on a $7,622,000 contract in 2020 to construct an office building. During...
Flounder, Inc. began work on a $7,622,000 contract in 2020 to construct an office building. During 2020, Flounder, Inc. incurred costs of $1,681,750, billed its customers for $1,162,000, and collected $909,000. At December 31, 2020, the estimated additional costs to complete the project total $3,123,250. Prepare Flounder’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT