Question

If you had a Job Costing job that had $100 in DM, $200 of DL and...

If you had a Job Costing job that had $100 in DM, $200 of DL and $150 of Applied Overhead the customer would be charged?

$450 of your cost plus a profit margin determined by management.

$350
$300
$450

Homework Answers

Answer #1

Direct materials = $100

Direct labor = $200

Actual overhead = $150

Total cost of the job = Direct materials + Direct labor + Actual overhead

= 100+200+150

= $450

Over the total cost of the job, there must a profit margin. Hence, the customer would be charged $450 of the cost plus a profit margin determined by management.

First option is correct.

Please give a positive rating if you are satisfied with this solution and if you have any query kindly ask.

Thanks!!!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
XYZ Company uses a job order costing system and has established a pre-determined overhead rate of...
XYZ Company uses a job order costing system and has established a pre-determined overhead rate of 145% of direct labor cost. Job #231 was charged with direct materials of $69,000 and had a total cost of $228,250. Calculate the amount of applied overhead charged to Job #231.
ABC Company began operations during 2022 and employs a job-order costing system with departmental overhead rates....
ABC Company began operations during 2022 and employs a job-order costing system with departmental overhead rates. Overhead from both Department A and Department B is assigned to jobs on the basis of direct labor hours. Below is a summary of events and transactions that occurred during 2022: a. ABC Company had the following estimates for 2022: Dept. A Dept. B Total Overhead cost $136,500 $192,000 $328,500 Direct labor hours 14,000 16,000 30,000 b. ABC Company began work on three jobs....
2. Job Order Costing – Application of Overhead using a pre-determined OH rate (4pts):   Skaro, Ltd....
2. Job Order Costing – Application of Overhead using a pre-determined OH rate (4pts):   Skaro, Ltd. is a manufacturer that uses a job-order costing system. Assume Skaro uses a single plantwide predetermined Factory OH rate to apply overhead, and bases their predetermined OH rate on machine hours (Mh). At the beginning of 2020, the firm made the following estimates for the upcoming year: Estimated Direct labor hours (DLh) 5,100 DLh Estimated Machine hours (Mh) 22,000 Mh Estimated total Variable Factory...
Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $710. During July,...
Job-Order Costing Variables On July 1, Job 46 had a beginning balance of $710. During July, prime costs added to the job totaled $600. Of that amount, direct materials were three times as much as direct labor. The ending balance of the job was $1,600. Required: 1. What was overhead applied to the job during July? $ 2. What was direct materials for Job 46 for July? Direct labor? If rounding is required, round your answers to the nearest cent....
A company which uses a job-costing system, had two jobs in process at the start of...
A company which uses a job-costing system, had two jobs in process at the start of February 2018: Job no. J6 with a cost of $110,000 and job no. F1 with a cost of $22,000. The following information is available: The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,366,000 and 102,000 hours, respectively. The company worked on four jobs during February. Direct materials used, direct...
Chirico Manufacturing Company uses job costing system. The following job cost records were provided for January,...
Chirico Manufacturing Company uses job costing system. The following job cost records were provided for January, the company’s first month of operations: Job 1 Job 2 Job 3 Job 4 Job 5 Direct materials used $100 $400 $300 $200 $400 Direct labor cost 300 600 200 500 100 Allocated overhead 300 600 200 500 100 Total $700 $1,600 $700 $1,200 $600 Date started 01/02 01/10 01/20 01/25 01/22 Date completed 01/18 01/20 01/30 02/02 02/10 Date delivered to customer 01/20...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows: Zayner Company is a job order costing company that uses activity-based costing (ABC) to apply manufacturing overhead to different jobs. Zayner identified three activities and the related cost drivers. The budgeted information (budget) for the year is as follows: Activity Cost Driver Amount of Driver Engineering...
The Eagles Corporation uses a normal job-order costing system in its only production department. Overhead is...
The Eagles Corporation uses a normal job-order costing system in its only production department. Overhead is applied to jobs by a plant-wide overhead rate based on direct labor hours. The first year of operation began on December 1, 2016. During the month of December, Eagles Corporation purchased direct material with a total cost of $4,000. Of the $4,000, Eagles Corporation used $500 on Job 100. Job 100 was the only job worked during the month of December. Eagles Corporation also...
Morrow Corporation had only one job in process during May—Job X32Z—and had no finished goods inventory...
Morrow Corporation had only one job in process during May—Job X32Z—and had no finished goods inventory on May 1. Job X32Z was started in April and finished during May. Data concerning that job appear below:         Job X32Z Beginning balance $ 5,000 Charged to the job during May Direct materials $ 8,000 Direct labor $ 2,000 Manufacturing overhead applied $ 4,000 Units completed 100 Units in process at the end of May 0 Units sold during May 40 In May, overhead...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct...
In its job-order costing system, Morris Equipment Company uses a predetermined overhead rate based on direct labor-hours. At the start of the year, MOH cost was estimated at $100,000 for the year. And, the number of DL hours to be used during the year was estimated at 40,000. In September, Job #274 was completed at a cost of $5,000 in direct materials and $2,400 in direct labor. The labor rate is $6 per hour. By the end of the year,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT