Question

Zayner Company is a job-order costing firm that use activity based costing to apply overhead to...

Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:
Zayner Company is a job order costing company that uses activity-based costing (ABC) to apply manufacturing overhead to different jobs. Zayner identified three activities and the related cost drivers. The budgeted information (budget) for the year is as follows:

Activity Cost Driver Amount of Driver

Engineering design $ 120,000 Engineering Hours 3,000 hrs
Purchasing 80,000 Number of parts 10,000 parts
Other overhead 250,000 Direct labor hours 40,000 hours

Zayner worked on five jobs in July. Data are as follows:

Job # 60 Job # 61 Job # 62 Job # 63 Job # 64

Balance, 7/1 $ 32,450 $ 40,770 $ 29,090 $ 0 $ 0
Direct materials $ 26,000 $ 37,900 $ 25,350 $ 11,000 $ 13,560
Direct labor $ 40,000 $ 38,500 $ 43,000 $ 20,900 $ 18,000
Engineering hours 20 10 15 100 200
Number of parts 150 180 200 500 300
Direct labor hours 2,500 2,400 2,600 1,200 1,100

As of July 31, jobs 60 and 62 were completed and sold. The remaining jobs remain in process.

Required:

1. Calculate the activity rates for each of the three manufacturing overheads.
2. Prepare job order cost sheets for each job that show all costs through July 31.
3. What is the cost of each job at the end of July?

Homework Answers

Answer #1
Req 1.
Activity Total OH Drivers Rate
Engineering design 120000 3000 40 per hour
Purchasing 80000 10000 8 per part
Other overheads 250000 40000 6.25 per hour
Req 2 and 3
JOB no. 60 61 62 63 64
Beginning balance 32450 40770 29090 0 0
Current cost
Material cost 26000 37900 25350 11000 13560
Labour cost 40000 38500 43000 20900 18000
Activity cost
Engineering design@ 40 per hour 800 400 600 4000 8000
Purchasing @8 per part 1200 1440 1600 4000 2400
Other overheads @6.25 per DLH 15625 15000 16250 7500 6875
TOTAL COST 116075 134010 115890 47400 48835
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost    Driver Amount of Driver Materials handling $ 72,000      Number of moves 3,000   Engineering 165,000      Number of change orders 10,000   Other overhead 280,000      Direct labor hours 50,000   Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44...
ob Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
ob Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $117,500 Number of moves 5,000 Engineering 128,000 Number of change orders 8,000 Other overhead 265,200 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct...
Sneffy Company has a job-order costing system and uses a predetermined overhead rate based on direct labor-hours to apply manufacturing overhead to jobs. Manufacturing overhead cost and direct labor hours were estimated at $100,000 and 25,000 hours, respectively, for the year. In July, Job #334 was completed at a cost of $5,000 in direct materials and $2,500 in direct labor. The labor rate is $5 per hour. By the end of the year, Sneffy had worked a total of 45,000...
A company has identified the following overhead costs and cost drivers for the coming year:     ...
A company has identified the following overhead costs and cost drivers for the coming year:               Budgeted   Overhead Item   Cost Driver Budgeted Cost    Activity Level   Machine setup   Number of setups $ 25,300           220           Inspection   Number of inspections 124,200         4,600           Material handling   Number of material moves 99,200         6,200           Engineering   Engineering hours 12,400         620                  Budgeted direct labor cost was $130,550 and budgeted direct material cost was $369,540. The following information was collected on...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following...
Calculating Activity-Based Costing Overhead Rates Assume that manufacturing overhead for Goldratt Company consisted of the following activities and costs: Setup (1,000 setup hours) $118,000 Production scheduling (400 batches) 60,000 Production engineering (60 change orders) 150,000 Supervision (2,000 direct labor hours) 46,000 Machine maintenance (12,000 machine hours) 60,000 Total activity costs $434,000 The following additional data were provided for Job 845: Direct materials costs $7,000 Direct labor cost (5 Milling direct labor hours;35 Finishing direct labor hours) $1,000 Setup hours 5...
X Company uses an activity-based costing overhead allocation system. It has identified three activities - Setup,...
X Company uses an activity-based costing overhead allocation system. It has identified three activities - Setup, Product testing, Packaging - and their respective cost drivers - setup hours, tests, packages. Budgeted activity costs in 2018 were as follows: Activity Budgeted Cost Setup $108,000 Product testing 58,600 Packaging 58,700 The following 2018 cost driver information is available for one of its products, Product X, and for all of its products (including Product X): Product X All Products setup hours 29,700 771,429...
4.) X Company uses an activity-based costing allocation system. On January 1, 2020, its accountant budgeted...
4.) X Company uses an activity-based costing allocation system. On January 1, 2020, its accountant budgeted the following costs and cost drivers for three of the activities that are used in the ABC system: Activity   Budgeted cost   Cost driver Assembly   $134,000   92,700 parts Packaging   $80,400   13,000 finished units Purchasing   $53,600   4,700 purchase orders In May of 2020, 563 units of Product C were finished, requiring $10,100 of direct materials, 5,000 direct labor hours, 1,410 parts, and 34 purchase orders. How...
A firm produces two products, X and Y and uses activity based costing to allocate overhead...
A firm produces two products, X and Y and uses activity based costing to allocate overhead costs. The various activities undertaken by the firm and the overhead cost pools and cost drivers are summarised below. Overhead activity Overhead cost Cost driver Cost driver consumption X Y Machining $125,000 Machine hours 25 75 Setups $ 80,000 Number of setups 24 36 Engineering $120,000 Engineering hours 120 80 If the firm uses the above cost drivers to allocate the overhead of each...
x company uses an activity based costing allocation system. January 1, 2020 its accountant budgeted the...
x company uses an activity based costing allocation system. January 1, 2020 its accountant budgeted the following costs and cost drivers for there of the activities that are used in the ABC System: Activity Budgeted Cost Cost Driver Packaging 50400 10000 finished units Assembly 84000 99400 Parts Purchasing 33600 4900 Purchase Orders In May of 2020, 690 units of Product C were finished, requiring $18,300 of direct materials, 5,000 direct labor hours, 1,220 parts, and 34 purchase orders. How much...
Parker Company has a job-order costing system and uses a pre-determined overhead rate based on direct...
Parker Company has a job-order costing system and uses a pre-determined overhead rate based on direct labor hours to apply manufacturing overhead to jobs. At the beginning of the year, manufacturing overhead and direct labor hours for the year were estimated at $50,000 and 25,000 hours respectively. In June, Job #461 was started, completed, and sold to a customer. Materials cost on the job totaled $4,000, and labor costs were $5 per hour and totaled $1,500. Sales commissions incurred on...