Question

ABC Company began operations during 2022 and employs a job-order costing system with departmental overhead rates....

ABC Company began operations during 2022 and employs a
job-order costing system with departmental overhead
rates. Overhead from both Department A and Department B
is assigned to jobs on the basis of direct labor hours.
Below is a summary of events and transactions that
occurred during 2022:

a.  ABC Company had the following estimates for 2022:

                        Dept. A      Dept. B       Total
Overhead cost           $136,500     $192,000     $328,500
Direct labor hours        14,000       16,000       30,000

b.  ABC Company began work on three jobs. Information
    about these three jobs appears below:

                             Job #1      Job #2      Job #3
Direct materials used      $ 71,400    $122,000    $103,000
Direct labor cost          $117,600    $ 93,600    $100,800       
DL hours in Dept. A           5,200       3,600       3,200
DL hours in Dept. B           4,600       4,200       5,200  

c.  Job #1 and Job #3 were completed during 2022. Job #2
    was not completed. In addition, Job #1 was sold during
    2022 whereas Job #3 was not sold.

d.  When Job #1 was sold to the customer, ABC Company charged
    the customer 150% of the total cost to manufacture Job #1.

Calculate ABC Company's work in process inventory balance at
December 31, 2022.
Calculate the total selling price charged to the customer for
Job #1.

Homework Answers

Answer #1
OH rate
Deptt A Deptt B
Overheads cost 136500 192000
Divide Total DLH 14000 16000
OH rate per DLH 9.75 12
Job 1 Job 2 Job 3
Direct material cost 71400 122000 103000
Direct labour cost 117600 93600 100800
Overheads applied
Deptt A(@ 9.75 per DLH) 50700 35100 31200
Depttt B (@12 per DLH) 55200 50400 62400
Total cost 294900 301100 297400
Total cost of Job 1 294900
Add: Mrkup @50% 147450
Selling price charged for Job 1 442350
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ABC Company applies overhead to products using a pre-determined overhead rate of 80% of direct labor...
ABC Company applies overhead to products using a pre-determined overhead rate of 80% of direct labor cost. During 2022, ABC Company began work on three jobs. Information relating to these three jobs appears below: Job A Job B Job C direct materials ....... $55,000 $75,000 $87,000 direct labor ........... $42,000 $39,000 $64,000 By the end of 2022, Job A and Job C had been completed. Job B was not completed by the end of 2022. Additionally, by the end of...
ABC Company applies overhead to products using a pre-determined overhead rate of 80% of direct labor...
ABC Company applies overhead to products using a pre-determined overhead rate of 80% of direct labor cost. During 2022, ABC Company began work on three jobs. Information relating to these three jobs appears below: Job A Job B Job C direct materials ....... $55,000 $75,000 $71,000 direct labor ........... $42,000 $39,000 $64,000 By the end of 2022, Job A and Job C had been completed. Job B was not completed by the end of 2022. Additionally, by the end of...
ABC Company applies overhead to products using a pre-determined overhead rate of 80% of direct labor...
ABC Company applies overhead to products using a pre-determined overhead rate of 80% of direct labor cost. During 2022, ABC Company began work on three jobs. Information relating to these three jobs appears below: Job A Job B Job C direct materials ....... $55,000 $75,000 $75,000 direct labor ........... $42,000 $39,000 $47,000 By the end of 2022, Job A and Job C had been completed. Job B was not completed by the end of 2022. Additionally, by the end of...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $135,000 for the year and the estimated direct labor hours were 15,000 hours. In May, Job #378 was completed. Direct materials totaled $8,500. Total labor costs were $14,000 at $16 per hour. At the end of the year, it was determined that the company worked 16,000 direct labor...
A company began operations on January 1, 20x3. The company uses a job order system and...
A company began operations on January 1, 20x3. The company uses a job order system and started the following jobs during January 20x3: Job 101 Job 102 Job 103 Direct materials $18422 $24413 $35988 Direct labour hours 971 1387 737 Additional information is as follows: Total estimated overhead $302539 Total estimated direct labour hours 19248 Actual direct labour rate $19 per direct labour hour All three jobs were completed by the end of January 20x3. Finished goods at January 31,...
The York Co. uses a job order cost system and applies factory overhead to individual jobs...
The York Co. uses a job order cost system and applies factory overhead to individual jobs by using predetermined overhead rates. In department X, overhead is applied on the basis of machine hours, and in department Y, on the basis of direct labor hours. At the beginning of the current year, management made the following budget estimates: Dept X Dept Y Direct Labor $210,000 $384,000 Factory Overhead $216,000 $105,000 Machine Hours 36,000 900 Direct Labor Hours 18,000 25,000 Production order...
The York Co. uses a job order cost system and applies factory overhead to individual jobs...
The York Co. uses a job order cost system and applies factory overhead to individual jobs by using predetermined overhead rates. In department X, overhead is applied on the basis of machine hours, and in department Y, on the basis of direct labor hours. At the beginning of the current year, management made the following budget estimates: Dept X Dept Y Direct Labor $210,000 $384,000 Factory Overhead $216,000 $105,000 Machine Hours 36,000 900 Direct Labor Hours 18,000 25,000 Production order...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis...
Gitano Products operates a job-order costing system and applies overhead cost to jobs on the basis of direct materials used in production (not on the basis of raw materials purchased). Its predetermined overhead rate was based on a cost formula that estimated $110,500 of manufacturing overhead for an estimated allocation base of $85,000 direct material dollars to be used in production. The company has provided the following data for the just completed year:         Purchase of raw materials $...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT