Chirico Manufacturing Company uses job costing system. The following job cost records were provided for January, the company’s first month of operations: Job 1 Job 2 Job 3 Job 4 Job 5 Direct materials used $100 $400 $300 $200 $400 Direct labor cost 300 600 200 500 100 Allocated overhead 300 600 200 500 100 Total $700 $1,600 $700 $1,200 $600 Date started 01/02 01/10 01/20 01/25 01/22 Date completed 01/18 01/20 01/30 02/02 02/10 Date delivered to customer 01/20 01/25 02/02 02/05 02/15 There was no inventory of any kind at the beginning of January. 3. The amount of cost of goods manufactured for January is A) $2,300. B) $1,800. C) $4,800. D) $3,000. 4. The amount of cost of goods sold for January is A) $4,800. B) $2,300. C) $3,000. D) $1,800. 5. The amount of ending work in process as of January 31st is A) $3,000. B) $1,800. C) $2,300. D) $4,800.
Jobs | 1 | 2 | 3 | 4 | 5 | |
Direct materials used | $100.00 | $400.00 | $300.00 | $200.00 | $400.00 | |
Direct labor cost | $300.00 | $600.00 | $200.00 | $500.00 | $100.00 | |
Allocated Overhead | $300.00 | $600.00 | $200.00 | $500.00 | $100.00 | |
Total Cost | $700.00 | $1,600.00 | $700.00 | $1,200.00 | $600.00 | |
Date Completed | 01/18 | 01/20 | 01/30 | 02/02 | 02/10 | |
Date delivered to customer | 01/20 | 01/25 | 02/02 | 02/05 | 02/15 | |
Job Status | COGM | COGM | COGM | |||
Job Status | COGS | COGS | ||||
Job Status | WIP | WIP | ||||
Cost of goods manufactured = Job 1 + Job 2 + Job 3 = $700+$1600+$700 = $3000 | ||||||
The answer is Option D. | ||||||
Cost of goods sold = Job 1 + Job 2 = $700 + $1600 = $2300 | ||||||
The answer is Option B. | ||||||
Ending work in process = Job 4 + Job 5 = $1200 + $600 = $1800 | ||||||
The answer is Option B. | ||||||