Question

A company which uses a job-costing system, had two jobs in process at the start of...

A company which uses a job-costing system, had two jobs in process at the start of February 2018: Job no. J6 with a cost of $110,000 and job no. F1 with a cost of $22,000. The following information is available:

  • The company applies manufacturing overhead on the basis of machine hours. Budgeted overhead and machine activity for the year were anticipated to be $3,366,000 and 102,000 hours, respectively.
  • The company worked on four jobs during February. Direct materials used, direct labor incurred, and machine hours consumed were:

Job No.

Direct Material

Direct Labor

Machine Hours

J6

         152,000

       118,000

          1,500

F1

         192,000

       101,500

         2,700

F2

         212,000

      135,000

         3,000

F3

          70,000

        85,000

          1,700

  • Manufacturing overhead during February included charges for depreciation ($104,000), indirect labor ($90,000), indirect materials used ($50,000), and other factory costs ($48,000).
  • Fallback completed job no. J6, job no. F1, and job no. F2. Job no. J6 was sold for cash, producing a gross profit of $142,600 for the firm. Job no. F1 was sold on account, producing a gross profit of $104,000 for the firm.

Answer and Show Work:

  1. Compute the company's predetermined overhead application rate. State it in terms of cost per machine hour.

Predetermined overhead rate per machine hour:

  1. Compute Total Manufacturing costs (use applied overhead – not actual overhead).

Total manufacturing costs:

  1. Compute the (unadjusted) Cost of Goods Sold.

Cost of goods sold:

4. Compute the Cost of Goods Manufactured (use applied overhead – not actual overhead).

Cost of goods manufactured:

5. Compute the cost of Ending Work-in-Process Inventory (use applied overhead – not actual overhead).

Cost of Ending Work-In-Process Inventory:

6. Compute (and identify) the amount of over- or under-applied overhead.

Over- or under-applied overhead (and which one):

Homework Answers

Answer #1

Hi

Let me know in case you face any issue:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis...
Harwood Company uses a job-order costing system that applies overhead cost to jobs on the basis of machine-hours. The company's predetermined overhead rate of $2.80 per machine-hour was based on a cost formula that estimates $232,400 of total manufacturing overhead for an estimated activity level of 83,000 machine-hours. Required: 1. Assume that during the year the company works only 78,000 machine-hours and incurs the following costs in the Manufacturing Overhead and Work in Process accounts: Compute the amount of overhead...
Southwestern Fashions, Inc. which uses a job-order costing system, had two jobs in process at the...
Southwestern Fashions, Inc. which uses a job-order costing system, had two jobs in process at the start of the year: job no. 101 ($84,100) and job no. 102 ($53,500). The following information is available:    a. The company applies manufacturing overhead on the basis of machine hours (based on practical capacity). Budgeted overhead and machine activity for the year were anticipated to be $824,000, and 16,000 hours, respectively. b. The company worked on four jobs during the first quarter. Direct...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
Melinda Spencer Company uses a job-order costing system. The company has two departments through which most...
Melinda Spencer Company uses a job-order costing system. The company has two departments through which most printing jobs pass. Selected budgeted and actual data for the past year follow: Designing Printing & Cutting Budgeted overhead $200,000 $500,000 Actual overhead $110,000 $520,000 Expected activity (direct labor hours) 50,000 20,000 Expected machine hours 10,000 50,000 Actual direct labor hours 52,000 9,000 Actual machine hours 10,500 52,000 During the year, several jobs were completed. Data pertaining to one such job, Job for Customer...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct labor-hour rate for the actual direct labor hours. Any overallocated or underallocated overhead is written-off to the cost of goods sold at the end of the month. During April 2019, ABC Manufacturing recorded the following: Budgeted manufacturing overhead costs: $400,000 Budgeted direct labor-hours: 20,000 DLHRS Budgeted machine hours: 16,000 MHRS Actual manufacturing overhead costs: $360,000 Actual direct labor-hours:   22,500 DLHRS Actual machine hours: 15,000...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined...
Benner Company uses a job-order costing system and applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. Manufacturing overhead and direct labor hours were estimated at $66,000 and 22,000 hours, respectively. In June, Job #461 was completed. Materials costs on the job totaled $4,923 and labor costs totaled $2,325 at $7.50 per hour (310 hours worked on this job). At the end of the year, it was determined that the company worked 23,975 direct...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
3. Bakerston Company is a manufacturing firm that uses job-order costing. The company's inventory balances were...
3. Bakerston Company is a manufacturing firm that uses job-order costing. The company's inventory balances were as follows at the beginning and end of the year: The company applies overhead to jobs using a predetermined overhead rate based on machine-hours. At the beginning of the year, the company estimated that it would work 33,000 machine-hours and incur $231,000 in manufacturing overhead cost. The following transactions were recorded for the year: raw materials beginning balance $14,000 ending $22,000 WIP beginning $27,000...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q.
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current year. The predetermined overhead rate is 30% of direct labor costs. The following cost information is available (all materials and time ticket information apply to direct costs): Job Material Requisitions Time Tickets 101 $91,000 $36,000 102 $67,000 $62,300 103 $47,000 $55,500 104 $35,700 $42,000 105 $39,000 $92,750 Part 1—Complete the job cost sheets for each job. Job No. 101 Job No. 102 Job No....