Tamarisk Construction Company has entered into a contract
beginning January 1, 2017, to build a parking complex. It has been
estimated that the complex will cost $601,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $903,000. The following data pertain to the construction
period.
2017 |
2018 |
2019 |
||||
Costs to date | $270,450 | $492,820 | $613,000 | |||
Estimated costs to complete | 330,550 | 108,180 | –0– | |||
Progress billings to date | 273,000 | 550,000 | 903,000 | |||
Cash collected to date | 243,000 | 500,000 | 903,000 |
(a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period.
b) Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period
Gross profit recognized each year under the Percentage of completion method = (Costs to date / Total estimated costs * Expected profit) - Previously recognized profits
Gross profit | |
2017 | $135,900 [{$270,450/($270,450+$330,550)*($903,000-$270,450-$330,550}-$0] |
2018 | $111,740 [{$492,820/($492,820+$108,180)*($903,000-$492,820-$108,180}-$135,900] |
2019 | $42,360 [{$613,000/$613,000*($903,000-$613,000)}-$135,900-$111,740] |
--------------------------------------------------------------------
(b)
Under Completed contract method, Gross profit is recognized only on the completion of the contract.
Gross profit | |
2017 | $0 |
2018 | $0 |
2019 | $290,000 ($903,000-$613,000) |
Get Answers For Free
Most questions answered within 1 hours.