Question

The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...

The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of gross profit to be recognized for the second year. a. 4,286 b. 1,619 c. 2,010 d. 1,842 e. 1,492

Homework Answers

Answer #1

Solution:

Total cost incurred till the end of second year = $4000 + $6000 = $10,000

Total Estimated cost = $4000 + $6000 + $4000 = $14,000

Percentage of completion till the end of second year = Total Cost incurred / Total Estimated cost = 10000 / 14000 = 71.43%

Total Estimated Gross profit = Contract price - Total Estimated cost = $20000 - $14000 = $6000

Gross Profit to be recognized in second year = (Total estimated Gross profit * Percentage of Completion) - Revenue already recognized in first year

= ($6000*71.43%) - $2667

= $1,619

Hence option "b" is correct.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
roblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
roblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,550,000 $ 4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows: First year Second year Third year Costs during year 40,000 80,000 50,000 Estimated costs to complete 120,000 80,000 -- How much gross profit should be recognized a the end of each year, assuming Jackson recognizes revenue over time according to percentage of completion?
A contractor at the end of its s second year working on a contract finds that...
A contractor at the end of its s second year working on a contract finds that the total estimated cost of the contract ($600,000) exceeds the contract price ($550,000). At the end of the first year of the contract, $20,000 of gross profit was recognized. The percentage of completion at the end of year 2 is 40%. What amount of loss is recognized for the second year? 20,000 50,000 70,000 40,000 10,000
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT