Question

The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...

The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of gross profit to be recognized for the second year.

a. 4,286

b. 1,619

c. 2,010

d. 1,842

e. 1,492

Homework Answers

Answer #1

Ans:

b.1619

Gross Profit =revenue – cost

Progress Complete=Cost Incurred till Now/Cost Incurred till Now +Expected cost to be incurred

Progress completion

S.NO

Progress Completion

1st year

2nd year

1

Cost Incurred till now

4000

10000

2

Expected cost

4000

3

Completion in %   1/1+2

71.43%

Profit to be recognised on percentage of completion method

=Revenue or contract Price - Cost * Percentage of Completion

=($20,000-$14,000)*71.43%=$4285.8

Gross Profit to be Recognised in Second Year=Total Gross Profit-Profit already recognised in Previous Periods= $4285.8-$2667=$1618.80=$1619 Rounded Off

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time...
The contract price for a long-term contract is $20,000. The contracting firm recognizes revenue over time based on the percentage of completion. $4,000 of cost was incurred on the contract in the first year, and $2,667 of gross profit was recognized at the end of the first year. $6,000 of cost was incurred on the contract in the second year, and estimated remaining cost to complete as of the end of the second year was $4,000. Compute the amount of...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
roblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to...
roblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,550,000 $ 4,250,000 $ 1,870,000 Estimated costs to complete as of year-end 5,950,000 1,700,000 0 Billings during...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the...
Problem 5-10 Long-term contract; revenue recognition over time [LO5-8, 5-9] [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the...
During 2018, Miners Inc. started a construction job with a contract price of $20,000. The job...
During 2018, Miners Inc. started a construction job with a contract price of $20,000. The job was completed in 2020 and information for the three years of construction is as follows: Required: Using the PERCENTAGE-OF-COMPLETION (cost-to-cost) method: Show and label all calculations. (a)   Calculate the total percentage complete for the contract at the end of each year. Round the percentage complete to two decimal places (ie. 12.34%). (b) Calculate the amount of gross profit that Miners should be recognized each...
A contractor at the end of its s second year working on a contract finds that...
A contractor at the end of its s second year working on a contract finds that the total estimated cost of the contract ($600,000) exceeds the contract price ($550,000). At the end of the first year of the contract, $20,000 of gross profit was recognized. The percentage of completion at the end of year 2 is 40%. What amount of loss is recognized for the second year? 20,000 50,000 70,000 40,000 10,000
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows: First year Second year Third year Costs during year 40,000 80,000 50,000 Estimated costs to complete 120,000 80,000 -- How much gross profit should be recognized a the end of each year, assuming Jackson recognizes revenue over time according to percentage of completion?
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT