roblem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021 | 2022 | 2023 | |||||||
Cost incurred during the year | $ | 2,550,000 | $ | 4,250,000 | $ | 1,870,000 | |||
Estimated costs to complete as of year-end | 5,950,000 | 1,700,000 | 0 | ||||||
Billings during the year | 2,050,000 | 4,750,000 | 3,200,000 | ||||||
Cash collections during the year | 1,825,000 | 4,100,000 | 4,075,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
Problem 6-10 (Algo) Part 1
Required:
1. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years.
Contract price | $10,000,000 | |||
2021 | 2022 | 2023 | ||
a) | Cost incurred during the year | $2,550,000 | $4,250,000 | $1,870,000 |
b) | Cost incurred to date | $2,550,000 | $6,800,000 | $8,670,000 |
c) | Estimated costs to complete | $5,950,000 | $1,700,000 | $0 |
d) | Total cost (b)+(c ) | $8,500,000 | $8,500,000 | $8,670,000 |
% of completion (b)/(d) | 30% | 80% | 100% | |
Revenue recognised | $3,000,000 | $8,000,000 | $10,000,000 | |
(10000000*0.3) | (10000000*0.8) | (10000000*1) | ||
Cost incurrred during the year | $2,550,000 | $4,250,000 | $1,870,000 | |
Gross profit | $450,000 | $3,750,000 | $8,130,000 |