Question

ABC Properties Ltd. has a contract to build a hotel for $3,000,000 to be received in...

ABC Properties Ltd. has a contract to build a hotel for $3,000,000 to be received in equal installments over 4 years. A reliable estimate of total cost of this contract is $1,500,000. During the first year, ABC will incur $400,000 in cost. During the second year, $500,000 of costs will be incurred. And then $300,000 will be incurred in the last two years. The company is quite sure that the project will be completed on time. According to the US GAAP, how much if the profit that can be reported in the second year of the project? Use percentage-of-completion method.

Homework Answers

Answer #1
Year Cost to date Estimated total cost
1 $400,000 $1,500,000
2 $900,000 $1,500,000
3 $1,200,000 $1,500,000
4 $1,500,000 $1,500,000

Expected profit = $3,000,000 - $1,500,000 = $1,500,000

Gross profit under the percentage of completion method = (cost to date / estimated total cost * expected profit) - previously recognized profit

Year 1 = ($400,000 / $1,500,000 * $1,500,000) - $0

= $400,000

Year 2 = ($900,000 / $1,500,000 * $1,500,000) - $400,000

= $500,000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000...
Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and fourth year is $0, based...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at...
Circle the correct answer symbol 6.Imar Construction company signed a contract to build new bridge at a contract price of $5,000,000 and total estimated cost of $4,000,000 the project will be completed within 4 years, the cost incurred to date for each period is, first year $1,000,000- second year $2,500,000- third year $3,200,000 and fourth year $4,100,000 while the estimasted cost to, complete the project for each each period is, first year $3,000,000- second year $1,700,000- third year $1,000,000 and...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Company ABC received a contract from company XYZ, worth $460 million to build a product. XYZ...
Company ABC received a contract from company XYZ, worth $460 million to build a product. XYZ will pay $50 million when the contract is signed, another $360 million at the end of the first year, and the $50 million balance at the end of second year. The expected cash outflows required to produce the product are estimated to be $150 million now, $95 million the first year, and $218 million the second year. The firm’s MARR is 27% for this...
Company ABC received a contract from company XYZ, worth $460 million to build a product. XYZ...
Company ABC received a contract from company XYZ, worth $460 million to build a product. XYZ will pay $50 million when the contract is signed, another $360 million at the end of the first year, and the $50 million balance at the end of second year. The expected cash outflows required to produce the product are estimated to be $150 million now, $95 million the first year, and $218 million the second year. The firm’s MARR is 5.1% for this...
On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed...
On Jan 1st, 2019, ACDC Co. signed a contract to construct a bridge to be completed by the end of 2021. The cataract price is $2,500,000. ACDC Co provides the following information for the project progress. Details 2019 2020 2021 Cost incurred to date $600,000 $1,400,000 $2,100,000 Estimated cost to complete $900,000 $600,000 $0 Customer billings $500,000 $600,000 $350,000 Cash collections $400,000 $500,000 $300,000 Assuming that ACDC uses the percentage of completion method, the cost incurred (used) in 2020 is...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs...
Jackson Construction has entered into a contract to build a large taco factory for $220,000. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows: First year Second year Third year Costs during year 40,000 80,000 50,000 Estimated costs to complete 120,000 80,000 -- How much gross profit should be recognized a the end of each year, assuming Jackson recognizes revenue over time according to percentage of completion?
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking...
Tamarisk Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $601,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $903,000. The following data pertain to the construction period. 2017 2018 2019 Costs to date $270,450 $492,820 $613,000 Estimated costs to complete 330,550 108,180 –0– Progress billings to date 273,000 550,000 903,000 Cash collected to date...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT