Question

On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...

On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows:

? 2010?? 2011?? 2012?

Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000

Estimated costs to complete?1,250,000? 880,000?-0-

Customer billings to date?1,100,000? 2,000,000?3,000,000

Collections to date?1,000,000? 1,750,000?2,950,000

1: Prepare Statement of Financial Position ends of 2010, 2012 and 2011(if any) under Percentage of-completion-method, completed-contract method.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 1: Prepare all entries for 2010, 2011, and 2012 for...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of...
On February 1, 2020, Bramble Contractors agreed to construct a building at a contract price of $5,820,000. Bramble estimated total construction costs would be $4,016,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date. $1,506,000 $2,652,000 $4,610,000 Estimated costs to complete. 2,510,000 1,768,000 -0- Customer billings to date 2,220,000 4,016,000 5,620,000 Collections to date 2,020,000 3,520,000 5,520,000 Fill in the...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $40,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          18,000         28,000 Collections to date                     5,000           15,000         26,000 If the company uses the percentage-of-completion method, the gross profit to be recognized in 2021 is___________________________ .
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           9,000          21,000         29,000 Collections to date                     4,000           14,000         25,000 If the company uses the percentage-of-completion method, an inventory/current liability of $___________should be shown on the balance sheet at December 31, 2021 related...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014...
Hardhat Contractors received a contract to construct a bridge for $4,500,000. Construction was begun in 2014 and completed in 2015. Cost and other data are presented below: 2014 2015 Costs incurred during the year 1,500,000 2,700,000 Estimated costs to complete 2,500,000 - Billings during the year 1,900,000 2,500,000 Cash collections during that year 1,700,000 2,600,000 Assume that Hardhat Contractors uses the percentage-of-completion method for revenue recognition. Compute the amount of gross profit recognized during 2014 and 2015. 2014 2015 Contract...
Gomez, Inc. began work in 2010 on contract #3814, which provided for a contract price of...
Gomez, Inc. began work in 2010 on contract #3814, which provided for a contract price of $7,200,000. Other details follow: 2010 2011 Costs incurred during the year $1,200,000 $3,675,000 Estimated costs to complete, as of December 31 3,600,000 0 Billings during the year 1,350,000 5,400,000 Collections during the year 900,000 5,850,000 14. Assume that Gomez uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2010 is a. $450,000. b. $600,000....
During 2017 Nilsen company started a construction job with a contract price of $2,400,000. The job...
During 2017 Nilsen company started a construction job with a contract price of $2,400,000. The job was completed in 2019. the following information was available 2017 2018 2019 cost incurred to date $750,000 $1,540,000 $2,000,000. Estimated cost $1,250,000 $660,000 -0-. Customer billing to date $650,000 $1,750,000 $2,400,000. Cash collection to date $450,000, $1,250,000 $2,250,000. Calculate the estimated gross profit and revenue to be recognized on this contract for the years ended december 31, 2017,2018 and 2019 assuming nilsen recognizes revenue...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2017 and completed in 2018. Cost and other data are presented below:                                                                         2017                2018 Costs incurred during the year                         $1,500 $1,300 Estimated costs to complete                              1,200 0 Billings during the year                                    1,200 1,300 Cash collections during the year                        1,000 1,500 Compute the amount of revenue and gross profit recognized during 2017 and 2018. Assume that McCombs recognizes revenue on this contract over...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following...
Curtis Co. entered into a long-term contract in 2020. The contract price was $2,250,000. The following data pertain to the first two years that the contract was in process. 2020                              2021               Costs incurred to date                                    $   570,000                  $1,557,500    Estimated costs to complete as of 12/31       1,330,000                         667,500 Billings to date                                                     650,000                     1,250,000    Cash collections to date                                     600,000                     1,150,000 1. Using the percentage-of-completion method: A. Compute gross profit to be reported in each...