Question

TASK:   Complete the MRP record for component C as it would appear at the beginning of...

TASK:   Complete the MRP record for component C as it would appear at the beginning of week 2.

MRP record for component C as it would appear at the beginning of week 1.

Week

1

2

3

4

5

6

Gross Requirements

15

30

25

25

10

20

Scheduled Receipts

40

0

0

0

0

0

Projected Available Balance

50

20

35

10

0

20

Planned Order Receipts

0

0

40

0

0

40

Planned Order Releases

40

0

0

40

0

0

During week 1, the following transactions occurred for component C:

  • The open order for 40 units due to be received at the start of week 1 was received on Monday of week 1 with a quantity of 35 (5 units of component C were scrapped on this order).
  • An inventory cycle count during week 1 revealed that ten units of component C were missing. Thus, an inventory adjustment of -10 was processed.
  • Five units of component C were actually disbursed (instead of the 15 units planned for disbursement to produce end products X and Y). (The MPS quantity of 10 in week 1 for product X was canceled as a result of a customer order cancellation.)
  • The MPS quantities for week 7 include 20 units for product X and 10 units for product Y.
  • Because of a change in customer order requirements, marketing has requested that the MPS quantity of 5 units for product X scheduled in week 4 be moved to week 3.
  • An order for 40 units was released.

Given this information, complete the MRP record for component C as it would appear at the beginning of week 2:

Week

2

3

4

5

6

7

Gross Requirements

Scheduled Receipts

Projected Available Balance

Planned Order Receipts

Planned Order Releases

Homework Answers

Answer #1

Please refer the formulas below for general calculations in MRP table:

t = current week

t-1 = previous week

scheduled receipt = SR (if given)

On-hand inventory / projected ending inventory (t) = on-hand inventory (t-1) - gross requirement (t)

(if on-hand inventory (t-1) > gross requirement (t))

On-hand inventory / projected ending inventory (t) = 0 (if on-hand inventory (t-1) <= gross requirement (t))

Net requirement (t) = 0 (if, on-hand inventory (t-1) >= gross requirement (t))

Net requirement (t) = Gross requirement (t) – [on-hand inventory (t-1) + scheduled receipt] (if, on-hand inventory (t-1) + SR(t) < gross requirement (t))

Planned receipt (t) = Net requirement (t)

Planned order release = Planned receipt (t), but offsetted ahead by lead time (i.e. Lead time 2, planned order release will be offsetted by 2 weeks)

MRP TABLE FOR C

Gross requirement in week 1:

As explained in question = 5 =15 - 10 ( The MPS quantity of 10 in week 1 for product X was canceled as a result of a customer order cancellation )

Scheduled receipt in week 1 = 25 = 40 - 5 (scrapped) - 10 (wrong count)

From the MRP in question we see....that there was an ending inventory of 25 already in week 1 (Monday). Hence, the projected available balance in week 1 (1st day) = scheduled receipt - gross requirement + Ending inventory (last week) = 25 - 5 + 25 = 45

Now, follow the formulas to calculate the cells of table.

Gross requirement of week 3 = 25 +5 =30

Gross requirement of week 4 =25 - 5 =20

Reason: marketing has requested that the MPS quantity of 5 units for product X scheduled in week 4 be moved to week 3.

Gross requirement in week 7 = 20 + 10 = 30

Reason: The MPS quantities for week 7 include 20 units for product X and 10 units for product Y

In the MRP Table the cell in green, is when 40 units has been released in week 3 to meet the demand of week 5.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
Problem L You work for a landscaping company. You need four poles and 2 cubic yards...
Problem L You work for a landscaping company. You need four poles and 2 cubic yards of mulch for every tree that is planted. Calculate the Material Requirements Plan below. The beginning inventory for each item has been given. Week Beg. Inv. 1 2 3 4 5 6 7 8 Quantity 72 65 30 64 Tree Lead Time = 1 wk Lot for Lot Gross Requirements Scheduled Receipts Projected On-Hand 2 Net Requirements Planned Order Receipts Planned Order Releases Poles...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule
Solve the MRP Item                         LLC    Leadtime      Lot Sizing Rule Skate 1 1 Lot for Lot Lace 1 1 FOQ = 500 Box 1 2 FOQ = 500 Board 1 2 Lot for Lot Wheel Assembly 2 1 FOQ = 800 Body 2 2 Lot for Lot Axle 2 1 Lot for Lot Hardware 2 3 FOQ = 1500 BOM                                                                         Draw Product Structures Here Boxed Skates       Skates (2)             Body             Axle (2)             Hardware             Wheel Assembly (2)       Laces (2)       Box Skateboard       Board       Wheel Assembly (4)       Axle (2)...
Question 1. How many statements are true? (A) 0 (B) 1 (C) 2 (D) 3 (E)...
Question 1. How many statements are true? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. Scheduled receipts are future receipts of past order releases Statement 2. The MPS contains the GR of the end -item. Statement 3. The POR is the inventory policy of the MRP Statement 4. MRP minimizes cost.
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks. Item D 1 2 3 4 5 6 Gross Requirements 100 300 100 400 100 50 On Hand/ Scheduled Receipts 700 Net Requirements A Planned Order Releases B The value of entry A is: A. 100 B. 200 C. 300 D. 700 E. None of the above. Reset Selection Question 19 Product D...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 10 15 45 10 30 90 20 45 160 Use the least total cost lot-sizing method to determine the quantity to order with...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Problem 5 Eighty units of end item E are needed at the beginning of week 6....
Problem 5 Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J now on hand. Lead times...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT