TASK: Complete the MRP record for component C as it would appear at the beginning of week 2.
MRP record for component C as it would appear at the beginning of week 1.
Week |
1 |
2 |
3 |
4 |
5 |
6 |
Gross Requirements |
15 |
30 |
25 |
25 |
10 |
20 |
Scheduled Receipts |
40 |
0 |
0 |
0 |
0 |
0 |
Projected Available Balance |
50 |
20 |
35 |
10 |
0 |
20 |
Planned Order Receipts |
0 |
0 |
40 |
0 |
0 |
40 |
Planned Order Releases |
40 |
0 |
0 |
40 |
0 |
0 |
During week 1, the following transactions occurred for component C:
Given this information, complete the MRP record for component C as it would appear at the beginning of week 2:
Week |
2 |
3 |
4 |
5 |
6 |
7 |
Gross Requirements |
||||||
Scheduled Receipts |
||||||
Projected Available Balance |
||||||
Planned Order Receipts |
||||||
Planned Order Releases |
Please refer the formulas below for general calculations in MRP table:
t = current week
t-1 = previous week
scheduled receipt = SR (if given)
On-hand inventory / projected ending inventory (t) = on-hand inventory (t-1) - gross requirement (t)
(if on-hand inventory (t-1) > gross requirement (t))
On-hand inventory / projected ending inventory (t) = 0 (if on-hand inventory (t-1) <= gross requirement (t))
Net requirement (t) = 0 (if, on-hand inventory (t-1) >= gross requirement (t))
Net requirement (t) = Gross requirement (t) – [on-hand inventory (t-1) + scheduled receipt] (if, on-hand inventory (t-1) + SR(t) < gross requirement (t))
Planned receipt (t) = Net requirement (t)
Planned order release = Planned receipt (t), but offsetted ahead by lead time (i.e. Lead time 2, planned order release will be offsetted by 2 weeks)
MRP TABLE FOR C
Gross requirement in week 1:
As explained in question = 5 =15 - 10 ( The MPS quantity of 10 in week 1 for product X was canceled as a result of a customer order cancellation )
Scheduled receipt in week 1 = 25 = 40 - 5 (scrapped) - 10 (wrong count)
From the MRP in question we see....that there was an ending inventory of 25 already in week 1 (Monday). Hence, the projected available balance in week 1 (1st day) = scheduled receipt - gross requirement + Ending inventory (last week) = 25 - 5 + 25 = 45
Now, follow the formulas to calculate the cells of table.
Gross requirement of week 3 = 25 +5 =30
Gross requirement of week 4 =25 - 5 =20
Reason: marketing has requested that the MPS quantity of 5 units for product X scheduled in week 4 be moved to week 3.
Gross requirement in week 7 = 20 + 10 = 30
Reason: The MPS quantities for week 7 include 20 units for product X and 10 units for product Y
In the MRP Table the cell in green, is when 40 units has been released in week 3 to meet the demand of week 5.
Get Answers For Free
Most questions answered within 1 hours.