Shown below is a partially completed MPS record for ball bearings.
a. Develop the MPS for ball bearings. ?(Enter your responses as integers. A response of? "0" is equivalent to being not? applicable.)
?Item: Ball bearings |
Order? Policy: 500 units |
|||||||||
Lead? Time: 1 week |
||||||||||
Quantity on? Hand: 400 |
Week |
|||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
|
Forecast |
550 |
300 |
350 |
400 |
300 |
400 |
150 |
300 |
400 |
350 |
Customer orders? (booked) |
300 |
350 |
250 |
250 |
150 |
150 |
150 |
150 |
100 |
150 |
Projected? on-hand inventory |
||||||||||
MPS quantity |
500 |
The projected available inventory is calculated using the following formula -
Where It = projected on-hand inventory of the period-t. Gt, Qt, and Otare the Forecast, MPS, and Orders of period-t respectively.
First, calculate the It's with MPS=0 for all the periods.
Next, starting from period 1, enter MPS=500 whenever the projected inventory is less than zero. Enter one period at a time.