Question

A project should be rejected if NPV is _____ and accepted if NPV is _____. Less...

A project should be rejected if NPV is _____ and accepted if NPV is _____.

Less than 1; greater than 1

Less than 0; greater than 0

Greater than 1; less than 1

Greater than 0; less than 0

Equal to 1; Greater than 1

Equal to 0; Greater than 0

Homework Answers

Answer #1

Less than 0 , Greater than 0 is the correct answer

The Net present value is the measure of the value of the project in present which is going to generate taking into consideration od risk which is the cost of capital as the firm need to incurr this cost to fund the project.

To calculate net present value we discount the future cash flows by the discount factor of the cost of the capital then add the total present value of each year to arrive at net present value, If it is less than 0 then it means it is giving lesser return than the cost of the capital and if it is more than 0 then it means it is giving higher return than the cost of the capital.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater...
A project should be rejected if IRR is _____ and accepted if IRR is _____. Greater than WACC; less than WACC Greater than MIRR; less than MIRR Less than WACC; greater than WACC Less than MIRR; greater than MIRR Less than 0; Greater than 0 Greater than 0; Less than 0
Which one of the following indicates a project should be accepted? A. NPV < 0 B....
Which one of the following indicates a project should be accepted? A. NPV < 0 B. IRR>WACC C. IRR<WACC D. NPV=1
An investment project is accepted if its NPV is less than its WACC. True False
An investment project is accepted if its NPV is less than its WACC. True False
1. NPV According to the text, the NPV rule states that "An investment should be accepted...
1. NPV According to the text, the NPV rule states that "An investment should be accepted if the NPV is positive and rejected if it is negative." What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV (or very close to zero) what would you do? Why? 2. FORECASTING ERROR (RISK) What is a "forecasting error"? Why is it important to the analysis of capital expenditure projects? please, original work.
The NPV rule states that, “An investment should be accepted if the net present value (...
The NPV rule states that, “An investment should be accepted if the net present value ( NPV) is positive and rejected if it is negative.” What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV ( or very close to zero) what would you do? Why?
Calculate the NPV and explain if the project should be accepted if the WACC is 10%...
Calculate the NPV and explain if the project should be accepted if the WACC is 10% and the initial investment is $35,000. Cash flows for years 1 through 3 are: $20,000; ($15,000) and $12,000. Why would you not use the IRR method to evaluate this project?
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based...
You are on the staff of Camden Inc. The CFO believes project acceptance should be based on the NPV, but Steve Camden, the president, insists that no project should be accepted unless its IRR exceeds the project’s risk-adjusted WACC. Now you must make a recommendation on a project that has a cost of $15,000 and two cash flows: $110,000 at the end of Year 1 and -$100,000 at the end of Year 2. The president and the CFO both agree...
An investment costs $200,000. If the present value (PV) of all the future cash flows is...
An investment costs $200,000. If the present value (PV) of all the future cash flows is $175,000, which of the following statements is correct? a. The project should be rejected since the Profitability Index is less than 1. b. The project should be rejected since the NPV is $25,000. c. The project should be accepted since the Profitability Index is greater than 0 d. The project should be rejected since the NPV is -$175,000.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT