Question

The NPV rule states that, “An investment should be accepted if the net present value (...

The NPV rule states that, “An investment should be accepted if the net present value ( NPV) is positive and rejected if it is negative.” What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV ( or very close to zero) what would you do? Why?

Homework Answers

Answer #1

If a project has a NPV equal to zero, it means that the project has produced a return rate which equals the required rate of return to accept the project. This rate of return is called Internal Rate of Return or IRR.

In such cases, the project which has to be accepted is decided on the basis of minimal requirement of cash inflows by respective projects. Another criteria to accept a Zero NPV project is that Shorter the project period will be accepted to the longer period project.

There could be other criteria like higher Accounting rate of return of a project, pay-back period method.

==========================

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. NPV According to the text, the NPV rule states that "An investment should be accepted...
1. NPV According to the text, the NPV rule states that "An investment should be accepted if the NPV is positive and rejected if it is negative." What does an NPV of zero mean? If you were a decision-maker faced with a project with a zero NPV (or very close to zero) what would you do? Why? 2. FORECASTING ERROR (RISK) What is a "forecasting error"? Why is it important to the analysis of capital expenditure projects? please, original work.
Choose the most accurate statement regarding the net present value of an investment or a financing...
Choose the most accurate statement regarding the net present value of an investment or a financing project: A) A financing project should be accepted if, and only if, the NPV is exactly equal to zero. B) An investment project should be accepted only if the NPV is equal to the initial cash flow. C)Any type of project should be accepted if the NPV is positive and rejected if it is negative D) An investment project that has positive cash flows...
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
1.Should NPV decision be accepted when the net present value is equal to zero?
1.Should NPV decision be accepted when the net present value is equal to zero?
Which of the following is not a net present value (NPV) decision rule? A        When choosing...
Which of the following is not a net present value (NPV) decision rule? A        When choosing among independent projects, select the one with the highest rate of return B        If an independent investment’s NPV is negative, reject the project C        If an independent investment’s NPV is positive, accept the project D        When choosing among mutually exclusive projects, select the one with the highest NPV
11. The discount rate that makes the net present value of an investment exactly equal to...
11. The discount rate that makes the net present value of an investment exactly equal to zero is the: A) Payback period. B) Internal rate of return. C) Average accounting return. D) Profitability index. E) Discounted payback period. 12. The internal rate of return (IRR) rule can be best stated as: A) An investment is acceptable if its IRR is exactly equal to its net present value (NPV). B) An investment is acceptable if its IRR is exactly equal to...
The discounted payback rule may cause: Both some positive net present value projects to be rejected;...
The discounted payback rule may cause: Both some positive net present value projects to be rejected; and some projects with negative net present values to be accepted. projects to be incorrectly accepted due to ignoring the time value of money. some positive net present value projects to be rejected. some projects with negative net present values to be accepted. the most liquid projects to be rejected in favor of less liquid projects.
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV)...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Hungry Whale Electronics is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $400,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $325,000 Year 2 $400,000 Year 3...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV)...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Happy Dog Soap Company is evaluating a proposed capital budgeting project (project Alpha) that will require an initial investment of $450,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $300,000 Year 2 $475,000 Year...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV)...
Net present value (NPV) Evaluating cash flows with the NPV method The net present value (NPV) rule is considered one of the most common and preferred criteria that generally lead to good investment decisions. Consider this case: Suppose Blue Hamster Manufacturing Inc. is evaluating a proposed capital budgeting project (project Beta) that will require an initial investment of $2,750,000. The project is expected to generate the following net cash flows: Year Cash Flow Year 1 $325,000 Year 2 $475,000 Year...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT